Skip to content
Gridcensus

UNKNOWN201502

Substation-Adjacent

Teller County, Colorado · WECC

DC Readiness
53.5
Fair / 100

UNKNOWN201502 is a substation-adjacent datacenter candidate site in Teller County, Colorado, interconnecting through WECC. It screens at 53.5/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN201502
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW

Speed to power

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPData102 - COS02
IXP distance6.1 mi
Fiber providers4
Fiber coverage25.0%

Site characteristics

Risk & environment

Water stress (WRI)High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score75/100

Location context

Nearest datacenterData102 - COS01
DC distance6.1 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.15¢/kWh
Industrial electricity9.66¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$2,307

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power15%
43
Fiber connectivity12%
62
Energy cost10%
50
Water risk8%
36
Natural hazard8%
75
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Teller County, ranked by DC Readiness.

Sites near UNKNOWN201502
SiteTypeVoltageCapacityQueue waitScore
EC Coal Teller CountyGreenfield1.7 yrs57.4
UNKNOWN202713Substation-Adjacent115 kV100 MW6.9 yrs57.0
UNKNOWN202750Substation-Adjacent115 kV100 MW6.9 yrs55.7
WOODLAND PARKSubstation-Adjacent115 kV100 MW6.9 yrs52.8
UNKNOWN201803Substation-Adjacent115 kV100 MW6.9 yrs52.0
DIVIDESubstation-Adjacent115 kV100 MW6.9 yrs51.7
UNKNOWN203961Substation-Adjacent115 kV100 MW6.9 yrs50.1
CRIPPLE CREEKSubstation-Adjacent69 kV50 MW6.9 yrs49.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN201502, Teller County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.