Skip to content
Gridcensus

Woolworth Building

Industrial

Logan County, Colorado · WECC

DC Readiness
47.7
Fair / 100

Woolworth Building is an industrial datacenter candidate site in Logan County, Colorado, interconnecting through WECC. It screens at 47.7/100 DC Readiness and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Speed to power

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPLunavi - Cheyenne
IXP distance87.4 mi
Fiber providers7
Fiber coverage36.6%

Site characteristics

Site typeIndustrial

Risk & environment

Flood zoneZone X
Water stress (WRI)High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score75/100

Location context

Nearest datacenterWindbreak Cable
DC distance59.3 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.94¢/kWh
Industrial electricity11.03¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$2,141

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
43
Fiber connectivity12%
61
Energy cost10%
50
Water risk8%
36
Natural hazard8%
75
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Logan County, ranked by DC Readiness.

Sites near Woolworth Building
SiteTypeVoltageCapacityQueue waitScore
OZ LoganGreenfield1.7 yrs58.5
OZ LoganGreenfield1.7 yrs58.3
RIDGECREST WINDFARMSubstation-Adjacent230 kV300 MW6.9 yrs53.6
UNKNOWN201533Substation-Adjacent230 kV300 MW6.9 yrs53.6
UNKNOWN208156Substation-Adjacent138 kV100 MW6.9 yrs49.6
STERLINGSubstation-Adjacent138 kV100 MW6.9 yrs49.6
TAP208155Substation-Adjacent138 kV100 MW6.9 yrs49.6
UNKNOWN205871Substation-Adjacent115 kV100 MW6.9 yrs49.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen