Skip to content
Gridcensus

Gunnison County, Colorado · WECC

DC Readiness
47.6
Fair / 100

SKITO is a substation-adjacent datacenter candidate site in Gunnison County, Colorado, interconnecting through WECC. It screens at 47.6/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationSKITO
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW

Speed to power

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPData102 - COS02
IXP distance116.5 mi
Fiber providers6
Fiber coverage18.7%

Site characteristics

Risk & environment

Flood zoneZone X
Water stress (WRI)High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score75/100

Location context

Nearest datacenterData102 - COS01
DC distance116.5 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.89¢/kWh
Industrial electricity10.04¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$2,924

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
43
Fiber connectivity12%
17
Energy cost10%
50
Water risk8%
36
Natural hazard8%
75
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Gunnison County, ranked by DC Readiness.

Sites near SKITO
SiteTypeVoltageCapacityQueue waitScore
EC Near 3 MW LLCGreenfield1.7 yrs56.0
EC Near 3 MW LLCGreenfield1.7 yrs54.9
EC Near 3 MW LLCGreenfield1.7 yrs54.8
EC Near 3 MW LLCGreenfield1.7 yrs54.7
EC Near 3 MW LLCGreenfield1.7 yrs54.2
EC Near 3 MW LLCGreenfield1.7 yrs54.2
EC Near 3 MW LLCGreenfield1.7 yrs54.1
EC Near 3 MW LLCGreenfield1.7 yrs53.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for SKITO, Gunnison County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.