Skip to content
Gridcensus

Garfield County, Colorado · WECC

DC Readiness
51.4
Fair / 100

DEBEQUE is a substation-adjacent datacenter candidate site in Garfield County, Colorado, interconnecting through WECC. It screens at 51.4/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationDEBEQUE
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityGRAND VALLEY POWERcooperativemoderate to large load · state default

Speed to power

Interconnection outlookConstrained
≈ 6.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPSTRATA Vernal Data Center
IXP distance104.5 mi
Fiber providers5
Fiber coverage17.0%

Site characteristics

Land contactGarfield County County Assessor

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score75/100

Location context

Nearest datacenterStrata Networks
DC distance104.5 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.39¢/kWh
Industrial electricity9.05¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$3,654

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track DEBEQUE

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
56
Fiber connectivity12%
56
Energy cost10%
50
Water risk7%
36
Natural hazard6%
75
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Garfield County, ranked by DC Readiness.

Sites near DEBEQUE
SiteTypeVoltageCapacityQueue waitScore
RIFLE UTESubstation-Adjacent345 kV600 MW6.9 yrs59.5
TAP203975Substation-Adjacent345 kV600 MW6.9 yrs59.4
WHEELERSubstation-Adjacent230 kV300 MW6.9 yrs57.7
UNKNOWN203894Substation-Adjacent230 kV300 MW6.9 yrs57.7
PARACHUTESubstation-Adjacent230 kV300 MW6.9 yrs57.7
EC Near Rifle Generating StationGreenfield——1.7 yrs57.6
STARKEY GULCHSubstation-Adjacent230 kV300 MW6.9 yrs57.6
EC Near Rifle Generating StationGreenfield——1.7 yrs57.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for DEBEQUE, Garfield County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.