DC Readiness
51.1
Fair / 100

COLGATE is a substation-adjacent datacenter candidate site in Yuba County, California, interconnecting through CAISO. It screens at 51.1/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 8.2 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationCOLGATE
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
UtilityPACIFIC GAS & ELECTRIC CO.investor ownedrestrictive to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookConstrained
≈ 8.2 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionCAISO
Queue depth227
Avg queue wait8.2 yrs

Connectivity

Nearest IXPQuest Roseville
IXP distance38.0 mi
Fiber providers5
Fiber coverage24.9%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score52/100

Location context

Nearest datacenterQuest Roseville
DC distance38.0 mi
County hazard (FEMA NRI)Relatively High (48)
DC tax incentiveNo
Commercial electricity29.96¢/kWh
Industrial electricity22.93¢/kWh
Cooling degree days1,000
Heating degree days2,500
Land price / acre$11,174

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track COLGATE

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power20%
40
Fiber connectivity12%
54
Energy cost10%
50
Water risk7%
24
Natural hazard6%
52
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
34
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Yuba County, ranked by DC Readiness.

Sites near COLGATE
SiteTypeVoltageCapacityQueue waitScore
OZ YubaGreenfield——5.7 yrs48.6
OZ YubaGreenfield——5.7 yrs48.1
UNKNOWN302130Substation-Adjacent115 kV100 MW8.2 yrs47.2
EC FFE Yuba CountyGreenfield——5.7 yrs46.7
BEALE AFB 1Substation-Adjacent69 kV50 MW8.2 yrs46.6
BANGORSubstation-Adjacent115 kV100 MW8.2 yrs46.5
BEALE AFB 2Substation-Adjacent69 kV50 MW8.2 yrs46.4
SMARTSVILLESubstation-Adjacent69 kV50 MW8.2 yrs46.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for COLGATE, Yuba County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.