Central Freeway, Parcel A

Industrial

San Francisco County, California · CAISO

DC Readiness
48.2
Fair / 100

At a glance

Central Freeway, Parcel A is an industrial datacenter candidate site in San Francisco County, California, scoring 48.2/100 DC Readiness — 11th of 52 scored sites in the county. It sits in the CAISO grid region and the PACIFIC GAS & ELECTRIC CO. service territory, where interconnection has averaged 7.6 years from request to operation.

Power & interconnection

UtilityPACIFIC GAS & ELECTRIC CO.investor ownedrestrictive to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookConstrained
≈ 8.3 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionCAISO
Queue depth227
Avg queue wait7.6 yrs
Recent queue wait8.3 yrs
Completion rate11%
Withdrawal rate89%

Connectivity

Nearest IXPThe Mission Street Center
IXP distance0.8 mi
Fiber providers13
Fiber coverage59.5%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score52/100

Location context

Nearest datacenterThe Mission Street Center
DC distance0.8 mi
County hazard (FEMA NRI)Relatively High (48)
DC tax incentiveNo
Commercial electricity21.45¢/kWh
Industrial electricity23.47¢/kWh
Cooling degree days1,000
Heating degree days2,500
Land price / acre$48,425

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Central Freeway, Parcel A

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Central Freeway, Parcel A compare with other sites in San Francisco County?

Central Freeway, Parcel A ranks 11th of 52 scored candidate sites in San Francisco County. Its 48.2/100 is roughly in line with the county average of 48.1. It is roughly in line with the California average of 45.4 and roughly in line with the national average of 53.2.

Against the California average, its strongest sub-score is fiber connectivity (91 vs 66) and its weakest is power availability (30 vs 36). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Central Freeway, Parcel A to power, fiber and other datacenters?

The nearest located transmission bottleneck is 30750_MOSSLD _230_30797_LASAGUIL_230_BR_1 _1 (CAISO), 18 miles away. For connectivity, the nearest internet exchange facility is The Mission Street Center at 0.8 miles. 13 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is The Mission Street Center, 0.8 miles away.

What are the flood, water and hazard risks at Central Freeway, Parcel A?

At the county level, FEMA's National Risk Index rates San Francisco County "Relatively High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
43
Fiber connectivity12%
91
Energy cost10%
50
Water risk7%
24
Natural hazard6%
52
Buildability7%
50
Labor market4%
50
DC cluster4%
100
Land / acreage3%
34
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in San Francisco County, ranked by DC Readiness.

Sites near Central Freeway, Parcel A
SiteTypeVoltageCapacityQueue waitScore
EC Near SF State UniversityGreenfield——7.6 yrs55.8
EC Near Hunters PointGreenfield——7.6 yrs55.4
OZ San FranciscoGreenfield——7.6 yrs50.4
EC Near Hunters PointGreenfield——7.6 yrs48.6
ForestFederal Excess——7.6 yrs48.4
Native PlanFederal Excess——7.6 yrs48.4
TownsendIndustrial——7.6 yrs48.3
Mission Bay Park 2Industrial——7.6 yrs48.3

Central Freeway, Parcel A: common questions

What is the DC Readiness score of Central Freeway, Parcel A?

Central Freeway, Parcel A scores 48.2/100 on the GridCensus DC Readiness scale, rated fair. It ranks 11th of 52 scored sites in San Francisco County. The San Francisco County average is 48.1 and the California average is 45.4.

Which electric utility serves Central Freeway, Parcel A?

PACIFIC GAS & ELECTRIC CO. (investor owned) holds the retail service territory that contains the site; its holding company is PACIFIC GAS & ELECTRIC CORPORATION.

What grid region is Central Freeway, Parcel A in?

Central Freeway, Parcel A is in the CAISO region. Projects interconnecting there have averaged a 7.6-year wait from queue request to operation.

How far is Central Freeway, Parcel A from an internet exchange?

The nearest internet exchange facility is The Mission Street Center, about 0.8 miles away; 13 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Central Freeway, Parcel A, San Francisco County, CA”, https://gridcensus.com/datacenter-sites/california/san-francisco-county/central-freeway-parcel-a-a2e49c86 (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Central Freeway, Parcel A, San Francisco County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.