Riverside County, California · CAISO

DC Readiness
48.9
Fair / 100

At a glance

CONCHO is a substation-adjacent datacenter candidate site in Riverside County, California, scoring 48.9/100 DC Readiness — 50th of 376 scored sites in the county. Its nearest substation is CONCHO (0 mi, 115 kV). It sits in the CAISO grid region and the SOUTHERN CALIFORNIA EDISON CO service territory, where interconnection has averaged 7.6 years from request to operation. GridCensus catalogs 100 MW of candidate capacity here.

Power & interconnection

Nearest substationCONCHO
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
UtilitySOUTHERN CALIFORNIA EDISON COinvestor ownedmoderate to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookConstrained
≈ 8.3 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionCAISO
Queue depth227
Avg queue wait7.6 yrs
Recent queue wait8.3 yrs
Completion rate11%
Withdrawal rate89%

Connectivity

Nearest IXPAISO Data Center
IXP distance46.9 mi
Fiber providers15
Fiber coverage63.4%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score52/100

Location context

Nearest datacenterAISO Data Center
DC distance46.9 mi
County hazard (FEMA NRI)Relatively High (48)
DC tax incentiveNo
Commercial electricity18.08¢/kWh
Industrial electricity14.89¢/kWh
Cooling degree days1,000
Heating degree days2,500
Land price / acre$19,831

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track CONCHO

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does CONCHO compare with other sites in Riverside County?

CONCHO ranks 50th of 376 scored candidate sites in Riverside County. Its 48.9/100 is roughly in line with the county average of 45.5. It is roughly in line with the California average of 45.4 and roughly in line with the national average of 53.2.

Against the California average, its strongest sub-score is power availability (56 vs 36) and its weakest is water (24 vs 27). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is CONCHO to power, fiber and other datacenters?

The nearest mapped substation, CONCHO, is about 0 miles away and operates at 115 kV. The nearest located transmission bottleneck is 99254_J.HINDS2_230_24806_MIRAGE _230_BR_1 _1 (CAISO), 5 miles away. For connectivity, the nearest internet exchange facility is AISO Data Center at 46.9 miles. 15 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is AISO Data Center, 46.9 miles away.

What are the flood, water and hazard risks at CONCHO?

At the county level, FEMA's National Risk Index rates Riverside County "Relatively High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power20%
43
Fiber connectivity12%
67
Energy cost10%
50
Water risk7%
24
Natural hazard6%
52
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
34
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Riverside County, ranked by DC Readiness.

Sites near CONCHO
SiteTypeVoltageCapacityQueue waitScore
DEVERSSubstation-Adjacent500 kV1,000 MW7.6 yrs57.7
Tequesquite LandfillBrownfield66 kV8 MW7.6 yrs57.0
RED BLUFFSubstation-Adjacent500 kV1,000 MW7.6 yrs56.6
OZ RiversideGreenfield——7.6 yrs54.7
OZ RiversideGreenfield——7.6 yrs54.2
OZ RiversideGreenfield——7.6 yrs54.1
CAPACITORSubstation-Adjacent345 kV600 MW7.6 yrs54.0
OZ RiversideGreenfield——7.6 yrs53.9

CONCHO: common questions

What is the DC Readiness score of CONCHO?

CONCHO scores 48.9/100 on the GridCensus DC Readiness scale, rated fair. It ranks 50th of 376 scored sites in Riverside County. The Riverside County average is 45.5 and the California average is 45.4.

What is the nearest substation to CONCHO?

The nearest mapped substation is CONCHO, about 0 miles away, at 115 kV. GridCensus catalogs 100 MW of candidate capacity for the site.

Which electric utility serves CONCHO?

SOUTHERN CALIFORNIA EDISON CO (investor owned) holds the retail service territory that contains the site; its holding company is SOUTHERN CALIFORNIA EDISON.

What grid region is CONCHO in?

CONCHO is in the CAISO region. Projects interconnecting there have averaged a 7.6-year wait from queue request to operation.

How far is CONCHO from an internet exchange?

The nearest internet exchange facility is AISO Data Center, about 46.9 miles away; 15 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “CONCHO, Riverside County, CA”, https://gridcensus.com/datacenter-sites/california/riverside-county/concho-ac44e732 (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for CONCHO, Riverside County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.