DC Readiness
46.6
Fair / 100

Mine Site is a former mine datacenter candidate site in Alameda, California, interconnecting through CAISO. It screens at 46.6/100 DC Readiness and a 8.2 yrs average interconnection-queue wait.

Power & interconnection

UtilityPACIFIC GAS & ELECTRIC CO.investor ownedrestrictive to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookConstrained
≈ 8.2 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionCAISO
Queue depth227
Avg queue wait8.2 yrs

Connectivity

Nearest IXPHurricane Electric Fremont 1
IXP distance13.5 mi
Fiber providers12
Fiber coverage64.4%

Site characteristics

Site typeFormer Mine
Former useMining: SandAndGravel; Status: Abandoned
Cleanup statusAbandoned

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score52/100

Location context

Nearest datacenterQES Computers
DC distance2.9 mi
County hazard (FEMA NRI)Relatively High (48)
DC tax incentiveNo
Commercial electricity29.86¢/kWh
Industrial electricity22.93¢/kWh
Cooling degree days1,000
Heating degree days2,500
Land price / acre$13,473

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Mine Site

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
40
Fiber connectivity12%
82
Energy cost10%
50
Water risk7%
24
Natural hazard6%
52
Buildability7%
50
Labor market4%
50
DC cluster4%
100
Land / acreage3%
34
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Alameda, ranked by DC Readiness.

Sites near Mine Site
SiteTypeVoltageCapacityQueue waitScore
TESLA Power ProjectBrownfield500 kV1,322 MW5.7 yrs66.5
NEWARK DISTRIBUTIONSubstation-Adjacent230 kV300 MW8.2 yrs58.9
TESLASubstation-Adjacent500 kV1,000 MW8.2 yrs58.6
EASTSHORESubstation-Adjacent230 kV300 MW8.2 yrs58.1
Juniper Networks SunnyvaleBrownfield115 kV1 MW5.7 yrs58.1
LOS ESTEROSSubstation-Adjacent230 kV300 MW8.2 yrs58.0
FREMONTSubstation-Adjacent230 kV300 MW8.2 yrs57.9
CASTRO VALLEYSubstation-Adjacent230 kV300 MW8.2 yrs56.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Mine Site, Alameda. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.