Greenfield (WINCHESTER - TAP152980)

Greenfield

Franklin County, Arkansas · MISO

DC Readiness
50.1
Fair / 100

Greenfield (WINCHESTER - TAP152980) is a greenfield datacenter candidate site in Franklin County, Arkansas, interconnecting through MISO. It screens at 50.1/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationWINCHESTER
Substation voltage161 kV
Available capacity100 MW

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth136
Avg queue wait2.8 yrs

Connectivity

Nearest IXPDC BLOX CHA1 - DCBLOX Chattanooga
IXP distance41.5 mi
Fiber providers12
Fiber coverage41.8%

Site characteristics

Site typeGreenfield

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score62/100

Location context

Nearest datacenterGoogle Jackson County Data Center
DC distance27.4 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.62¢/kWh
Industrial electricity6.41¢/kWh
Cooling degree days1,600
Heating degree days3,600
Land price / acre$5,951

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Greenfield (WINCHESTER - TAP152980)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
32
Speed to power20%
47
Fiber connectivity12%
58
Energy cost10%
50
Water risk7%
90
Natural hazard6%
62
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
47
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
45

Nearby comparable sites

Other scored datacenter candidate sites in Franklin County, ranked by DC Readiness.

Sites near Greenfield (WINCHESTER - TAP152980)
SiteTypeVoltageCapacityQueue waitScore
Franklin (TN)Brownfield—510 MW3.7 yrs66.5
EC Near Franklin (TN)Greenfield——3.7 yrs63.4
EC Near Franklin (TN)Greenfield——3.7 yrs63.4
WINCHESTERSubstation-Adjacent161 kV100 MW1.0 yrs62.2
DECHERDSubstation-Adjacent161 kV100 MW1.0 yrs62.1
NORTH COWANSubstation-Adjacent161 kV100 MW1.0 yrs62.0
EC Near Franklin (TN)Greenfield——3.7 yrs61.6
ESTILL SPRINGSSubstation-Adjacent161 kV100 MW1.0 yrs61.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.