Dover (OH)

Brownfield

Dover, Tuscarawas, Ohio · City of Dover - (OH)

Legacy capacity
4
MW

Dover (OH) is a coal plant in Dover, Tuscarawas, Ohio, retired 2007-06-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 4 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usecoal plant
Site typeretired_plant
Existing capacity4 MW
Retirement date2007-06-01
EIA plant ID#2914

Grid hookup & remediation

Nearest substation1.3 mi
OperatorCity of Dover - (OH)
Operator address303 East Broadway, Dover, OH, 44622
Why this site is datacenter-attractive: a coal plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near Dover (OH), ranked by DC Readiness.

Candidate sites near Dover (OH)
SiteTypeStateCountyVoltageCapacityQueue waitScore
SOUTH CANTON 765KVSubstation-AdjacentOHStark County765 kV1,000 MW3.2 yrs79.8
HIGHLANDSubstation-AdjacentOHStark County345 kV600 MW3.2 yrs77.6
SOUTH EAST CANTONSubstation-AdjacentOHStark County345 kV600 MW3.2 yrs74.6
UNKNOWN153863Substation-AdjacentOHStark County345 kV600 MW3.2 yrs74.2
Greenfield (KAMMER (765KV) - SOUTH CANTON )GreenfieldOHCarroll County765 kV1,000 MW3.2 yrs72.6
SOUTH CANTON 345KVSubstation-AdjacentOHStark County345 kV600 MW3.2 yrs72.0
MILES AVENUESubstation-AdjacentOHStark County138 kV100 MW3.2 yrs72.0
DALESubstation-AdjacentOHStark County138 kV100 MW3.2 yrs71.9

Nearby internet exchanges

See all datacenter sites in Ohio

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Dover (OH), Dover, Tuscarawas, Ohio. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.