HF Lee Plant

Brownfield

Goldsboro, Wayne, North Carolina · Duke Energy Progress - (NC)

Legacy capacity
508
MW

HF Lee Plant is a coal plant in Goldsboro, Wayne, North Carolina, retired 2012-10-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 508 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usecoal plant
Site typeretired_plant
Existing capacity508 MW
Retirement date2012-10-01
EIA plant ID#2709

Grid hookup & remediation

Nearest substation2.7 mi
OperatorDuke Energy Progress - (NC)
Operator address1677 Old Smithfield Road, Goldsboro, NC, 27530
Why this site is datacenter-attractive: a coal plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near HF Lee Plant, ranked by DC Readiness.

Candidate sites near HF Lee Plant
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN113479Substation-AdjacentNCJohnston County230 kV300 MW4.3 yrs69.8
UNKNOWN113480Substation-AdjacentNCJohnston County230 kV300 MW4.3 yrs67.5
TAP148003Substation-AdjacentNCWake County230 kV300 MW4.3 yrs66.7
TAP147988Substation-AdjacentNCJohnston County230 kV300 MW4.3 yrs65.5
TAP147987Substation-AdjacentNCJohnston County230 kV300 MW4.3 yrs65.2
UNKNOWN113509Substation-AdjacentNCJohnston County230 kV300 MW4.3 yrs64.4
UNKNOWN112699Substation-AdjacentNCWayne County230 kV300 MW4.3 yrs64.4
TAP148043Substation-AdjacentNCJohnston County230 kV300 MW4.3 yrs63.7

Nearby internet exchanges

See all datacenter sites in North Carolina

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.