Buck

Brownfield

Salisbury, Rowan, North Carolina · Duke Energy Carolinas, LLC

Legacy capacity
474
MW

Buck is a coal plant in Salisbury, Rowan, North Carolina, retired 2013-05-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 474 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usecoal plant
Site typeretired_plant
Existing capacity474 MW
Retirement date2013-05-01
EIA plant ID#2720

Grid hookup & remediation

Nearest substation0.3 mi
OperatorDuke Energy Carolinas, LLC
Operator address1555 Dukeville Rd, Salisbury, NC, 28145
Why this site is datacenter-attractive: a coal plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near Buck, ranked by DC Readiness.

Candidate sites near Buck
SiteTypeStateCountyVoltageCapacityQueue waitScore
WOODLEAF SWITCHING STATIONSubstation-AdjacentNCRowan County500 kV1,000 MW4.3 yrs73.5
UNKNOWN114573Substation-AdjacentNCCabarrus County230 kV300 MW4.3 yrs72.6
Greenfield (WOODLEAF SWITCHING STATION - M)GreenfieldNCRowan County500 kV1,000 MW4.3 yrs69.6
Greenfield (PLEASANT GARDEN - WOODLEAF SWI)GreenfieldNCRowan County500 kV1,000 MW4.3 yrs68.1
Greenfield (WOODLEAF SWITCHING STATION - M)GreenfieldNCRowan County500 kV1,000 MW4.3 yrs67.2
UNKNOWN114916Substation-AdjacentNCForsyth County230 kV300 MW4.3 yrs66.7
TAP169920Substation-AdjacentNCRowan County230 kV300 MW4.3 yrs66.4
UNKNOWN114688Substation-AdjacentNCRowan County100 kV50 MW4.3 yrs65.6

Nearby internet exchanges

See all datacenter sites in North Carolina

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Buck, Salisbury, Rowan, North Carolina. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.