City of Canandaigua - Phase I

Brownfield

Canandaigua, New York

Legacy capacity
2
MW

City of Canandaigua - Phase I is a former landfill site in Canandaigua, New York. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 2 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former useformer landfill site
Site typeepa_brownfield
Existing capacity2 MW

Grid hookup & remediation

Nearest substation5.6 mi
Cleanup statuscleanup_complete
Why this site is datacenter-attractive: a former landfill site of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near City of Canandaigua - Phase I, ranked by DC Readiness.

Candidate sites near City of Canandaigua - Phase I
SiteTypeStateCountyVoltageCapacityQueue waitScore
Emerson Street LandfillBrownfieldNYMonroe3 MW66.9
UNKNOWN125198Substation-AdjacentNYMonroe County115 kV100 MW3.5 yrs66.8
HOGAN RDSubstation-AdjacentNYOntario County115 kV100 MW3.5 yrs66.2
MORTIMERSubstation-AdjacentNYMonroe County115 kV100 MW3.5 yrs66.0
UNKNOWN125186Substation-AdjacentNYMonroe County115 kV100 MW3.5 yrs65.9
TAP138445Substation-AdjacentNYMonroe County115 kV100 MW3.5 yrs65.6
TAP138444Substation-AdjacentNYMonroe County115 kV100 MW3.5 yrs65.4
TAP138439Substation-AdjacentNYOntario County115 kV100 MW3.5 yrs65.4

Nearby internet exchanges

See all datacenter sites in New York

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for City of Canandaigua - Phase I, Canandaigua, New York. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.