Fulton (MO)
BrownfieldFulton, Callaway, Missouri · City of Fulton - (MO)
Fulton (MO) is a oil plant in Fulton, Callaway, Missouri, retired 2012-05-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 5 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.
Former use & capacity
Grid hookup & remediation
Nearby datacenter candidate sites
Scored candidate sites near Fulton (MO), ranked by DC Readiness.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| TAP140550 | Substation-Adjacent | MO | Boone County | 345 kV | 600 MW | 1.4 yrs | 74.6 |
| CALLAWAY | Substation-Adjacent | MO | Callaway County | 345 kV | 600 MW | 1.4 yrs | 73.1 |
| TAP140550 | Substation-Adjacent | MO | Callaway County | 345 kV | 600 MW | 4.6 yrs | 72.2 |
| UNKNOWN117810 | Substation-Adjacent | MO | Callaway County | 345 kV | 600 MW | 1.4 yrs | 71.8 |
| TAP140561 | Substation-Adjacent | MO | Callaway County | 345 kV | 600 MW | 1.4 yrs | 69.4 |
| CALLAWAY | Substation-Adjacent | MO | Callaway County | 345 kV | 600 MW | 4.6 yrs | 68.3 |
| LOOSE CREEK | Substation-Adjacent | MO | Osage County | 345 kV | 600 MW | 1.4 yrs | 68.2 |
| UNKNOWN117848 | Substation-Adjacent | MO | Boone County | 161 kV | 100 MW | 1.4 yrs | 67.3 |
See all datacenter sites in Missouri →
Dataset updated . Screening estimates derived from public data sources.
Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Fulton (MO), Fulton, Callaway, Missouri. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.