Delta (MS)

Brownfield

Cleveland, Bolivar, Mississippi · Entergy Mississippi LLC

Legacy capacity
225
MW

Delta (MS) is a natural gas plant in Cleveland, Bolivar, Mississippi, retired 2012-12-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 225 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usenatural gas plant
Site typeretired_plant
Existing capacity225 MW
Retirement date2012-12-01
EIA plant ID#2051

Grid hookup & remediation

Nearest substation2.1 mi
OperatorEntergy Mississippi LLC
Operator address3964 Hwy 61, Cleveland, MS, 38732
Why this site is datacenter-attractive: a natural gas plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near Delta (MS), ranked by DC Readiness.

Candidate sites near Delta (MS)
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN110697Substation-AdjacentMSWashington County230 kV300 MW1.4 yrs65.7
UNKNOWN111259Substation-AdjacentMSCoahoma County115 kV100 MW1.4 yrs64.5
INDIANOLASubstation-AdjacentMSSunflower County230 kV300 MW1.4 yrs64.2
UNKNOWN111252Substation-AdjacentMSCoahoma County115 kV100 MW1.4 yrs63.9
DELTA (MS)Substation-AdjacentMSBolivar County115 kV100 MW1.4 yrs62.2
TAP142175Substation-AdjacentMSBolivar County115 kV100 MW1.4 yrs61.9
UNKNOWN110723Substation-AdjacentMSBolivar County115 kV100 MW1.4 yrs61.7
UNKNOWN110701Substation-AdjacentMSWashington County115 kV100 MW1.4 yrs61.4

See all datacenter sites in Mississippi

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Delta (MS), Cleveland, Bolivar, Mississippi. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.