Scottville

Brownfield

Scottville, Mason, Michigan · Wolverine Power Supply Coop

Legacy capacity
4
MW

Scottville is a oil plant in Scottville, Mason, Michigan, retired 2002-01-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 4 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former useoil plant
Site typeretired_plant
Existing capacity4 MW
Retirement date2002-01-01
EIA plant ID#1879

Grid hookup & remediation

Nearest substation4.5 mi
OperatorWolverine Power Supply Coop
Operator address525 West US 10, Scottville, MI, 49454
Why this site is datacenter-attractive: a oil plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near Scottville, ranked by DC Readiness.

Candidate sites near Scottville
SiteTypeStateCountyVoltageCapacityQueue waitScore
KEYSTONESubstation-AdjacentMIMason County345 kV600 MW1.4 yrs71.6
LUDINGTONSubstation-AdjacentMIMason County345 kV600 MW1.4 yrs70.2
UNKNOWN128917Substation-AdjacentMIMason County345 kV600 MW1.4 yrs69.3
TES FILER CITY STATIONSubstation-AdjacentMIManistee County138 kV100 MW1.4 yrs68.9
Greenfield (TALLMADGE - LUDINGTON)GreenfieldMIOceana County345 kV600 MW1.4 yrs67.1
UNKNOWN128881Substation-AdjacentMIManistee County138 kV100 MW2.2 yrs66.6
UNKNOWN145858Substation-AdjacentMILake County138 kV100 MW1.4 yrs66.4
Greenfield (TALLMADGE - LUDINGTON)GreenfieldMIOceana County345 kV600 MW1.4 yrs66.3

See all datacenter sites in Michigan

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Scottville, Scottville, Mason, Michigan. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.