B E Morrow

Brownfield

Comstock, Kalamazoo, Michigan · Consumers Energy Co - (MI)

Legacy capacity
36
MW

B E Morrow is a natural gas plant in Comstock, Kalamazoo, Michigan, retired 2014-03-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 36 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usenatural gas plant
Site typeretired_plant
Existing capacity36 MW
Retirement date2014-03-01
EIA plant ID#1696

Grid hookup & remediation

Nearest substation0.0 mi
OperatorConsumers Energy Co - (MI)
Operator address28th St., Comstock, MI, 49041
Why this site is datacenter-attractive: a natural gas plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near B E Morrow, ranked by DC Readiness.

Candidate sites near B E Morrow
SiteTypeStateCountyVoltageCapacityQueue waitScore
ARGENTASubstation-AdjacentMIKalamazoo County345 kV600 MW2.2 yrs73.7
TAP138973Substation-AdjacentMICass County345 kV600 MW2.2 yrs73.6
WEEDS LAKESubstation-AdjacentMIKalamazoo County345 kV600 MW2.2 yrs73.0
Greenfield (TAP138973 - ARGENTA)GreenfieldMICass County345 kV600 MW2.2 yrs71.8
FLOWERFIELDSubstation-AdjacentMISt. Joseph County138 kV100 MW2.2 yrs71.8
TAP141281Substation-AdjacentMIKalamazoo County138 kV100 MW2.2 yrs71.8
UNKNOWN128778Substation-AdjacentMIKalamazoo County138 kV100 MW2.2 yrs71.4
TAP145702Substation-AdjacentMISt. Joseph County138 kV100 MW2.2 yrs71.3

Nearby internet exchanges

See all datacenter sites in Michigan

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.