Venice

Brownfield

Venice, Madison, Illinois · Union Electric Co - (MO)

Legacy capacity
512
MW

Venice is a oil plant in Venice, Madison, Illinois, retired 2011-09-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 512 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former useoil plant
Site typeretired_plant
Existing capacity512 MW
Retirement date2011-09-01
EIA plant ID#913

Grid hookup & remediation

Nearest substation0.0 mi
Operator address701 Main Street, Venice, IL, 62090
Why this site is datacenter-attractive: a oil plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Site conditions & market — Madison County

County-level intelligence for this site's location — the power economics, water, hazard, connectivity, and workforce a developer screens before ever visiting. Assembled from FEMA NRI, BLS QCEW, FCC BDC, USGS water-use, and EIA.

Market & workforce

Total employment (laborshed)89,215
IT / tech employment65
Construction employment5,968
Land value$6,940/acre
Datacenter tax incentivesales_tax_exemption

Power economics & interconnection

Commercial power rate9.46¢/kWh
Industrial power rate4.60¢/kWh
Load growth (FERC-714)0.7%

Water & cooling

Water stressLow
Public water supply52.4 MGD
Industrial water use41.9 MGD
Cooling degree days1,100
Mean annual temp52°F

Hazard, flood & connectivity

FEMA risk index35.0 · Relatively High
Fiber providers13 · 47% served

County-level context — address-level utility offerings and flood zoning vary within the county. Confirm site-specific service with the utility and a Phase I ESA.

Nearby brownfield & retired-generation sites

A proximity screen of other retired-plant, contaminated, and EPA-flagged sites near Venice — the environmental neighborhood, ranked by legacy grid capacity.

SiteFormer useLegacy MWDistanceCleanup status
Merameccoal plant1,04120.1 mi—
Wood Rivercoal plant65014.0 mi—
Stallingsnatural gas plant958.4 mi—
Howard Bendoil plant4719.7 mi—
Belleville Landfill Projectformer landfill site1314.3 micleanup_complete
American Bottoms Solar Projectformer power_plant site25.6 micleanup_complete

Derived from GridCensus's retired-generator & EPA brownfield dataset. Not a substitute for an ASTM E1527 Phase I environmental radius report.

Get alerts

Track Venice

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Nearby datacenter candidate sites

Scored candidate sites near Venice, ranked by DC Readiness.

Candidate sites near Venice
SiteTypeStateCountyVoltageCapacityQueue waitScore
American Bottoms Solar ProjectBrownfieldMOSt. Louis345 kV2 MW3.8 yrs70.2
CAHOKIASubstation-AdjacentILSt. Louis city345 kV600 MW3.8 yrs69.2
TAP139481Substation-AdjacentILSt. Louis city345 kV600 MW3.8 yrs68.2
STALLINGSSubstation-AdjacentILMadison County345 kV600 MW3.8 yrs68.0
ROXFORDSubstation-AdjacentILMadison County345 kV600 MW3.8 yrs67.0
UNKNOWN121705Substation-AdjacentILSt. Louis city138 kV100 MW3.8 yrs66.4
TURKEY HILLSubstation-AdjacentILSt. Clair County345 kV600 MW3.8 yrs65.6
OZ St. ClairGreenfieldILSt. Clair——4.6 yrs65.5

Nearby internet exchanges

See all datacenter sites in Illinois →

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

Every site and score for Venice, Venice, Madison, Illinois is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.