Fernandina Plant
BrownfieldFernandina Beach, Nassau, Florida · Rayonier Advanced Materials
Fernandina Plant is a former biomass site in Fernandina Beach, Nassau, Florida, retired 2012-07-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 13 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.
Former use & capacity
Grid hookup & remediation
Nearby datacenter candidate sites
Scored candidate sites near Fernandina Plant, ranked by DC Readiness.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| UNKNOWN120554 | Substation-Adjacent | FL | Duval County | 230 kV | 300 MW | 5.8 yrs | 74.1 |
| FORT CAROLINE | Substation-Adjacent | FL | Duval County | 230 kV | 300 MW | 5.8 yrs | 73.5 |
| NAVAL SUBMARINE BASE KINGS BAY | Substation-Adjacent | GA | Camden County | 230 kV | 300 MW | 5.8 yrs | 73.4 |
| UNKNOWN111395 | Substation-Adjacent | GA | Camden County | 230 kV | 300 MW | 5.8 yrs | 73.2 |
| BLOUNT ISLAND | Substation-Adjacent | FL | Duval County | 230 kV | 300 MW | 5.8 yrs | 73.2 |
| UNKNOWN111400 | Substation-Adjacent | GA | Camden County | 230 kV | 300 MW | 5.8 yrs | 73.1 |
| UNKNOWN111398 | Substation-Adjacent | GA | Camden County | 230 kV | 300 MW | 5.8 yrs | 73.0 |
| TAP151528 | Substation-Adjacent | FL | Duval County | 230 kV | 300 MW | 3.6 yrs | 72.7 |
Nearby internet exchanges
- Cologix JAX1Jacksonville, FL · 33 networks
- SBA Edge - Jacksonville (JAX)Jacksonville, FL · 15 networks
- JAX NAPJacksonville, FL · 7 networks
- EdgeConneX Jacksonville (EDCJAX01)Jacksonville, FL · 6 networks
See all datacenter sites in Florida →
Dataset updated . Screening estimates derived from public data sources.
Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Fernandina Plant, Fernandina Beach, Nassau, Florida. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.