Central District Wastewater Treat Plant

Brownfield

Miami, Miami Dade, Florida · Miami Dade Water & Sewer Dept

Legacy capacity
5
MW

Central District Wastewater Treat Plant is a former biomass site in Miami, Miami Dade, Florida, retired 2014-11-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 5 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former useformer biomass site
Site typeretired_plant
Existing capacity5 MW
Retirement date2014-11-01
EIA plant ID#54623

Grid hookup & remediation

Nearest substation0.1 mi
Operator address3989 Rickenbacker cswy, Miami, FL, 33131
Why this site is datacenter-attractive: a former biomass site of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby brownfield & retired-generation sites

A proximity screen of other retired-plant, contaminated, and EPA-flagged sites near Central District Wastewater Treat Plant — the environmental neighborhood, ranked by legacy grid capacity.

SiteFormer useLegacy MWDistanceCleanup status
Lauderdalenatural gas plant1,79522.3 mi—
Port Evergladesoil plant1,71023.3 mi—
Turkey Pointoil plant81824.3 mi—
Cutlernatural gas plant23712.1 mi—
G W Iveynatural gas plant2327.3 mi—

Derived from GridCensus's retired-generator & EPA brownfield dataset. Not a substitute for an ASTM E1527 Phase I environmental radius report.

Get alerts

Track Central District Wastewater Treat Plant

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Nearby datacenter candidate sites

Scored candidate sites near Central District Wastewater Treat Plant, ranked by DC Readiness.

Candidate sites near Central District Wastewater Treat Plant
SiteTypeStateCountyVoltageCapacityQueue waitScore
LEVEESubstation-AdjacentFLMiami-Dade County500 kV1,000 MW1.0 yrs71.7
ANDYTOWNSubstation-AdjacentFLBroward County500 kV1,000 MW1.0 yrs69.7
UNKNOWN120065Substation-AdjacentFLMiami-Dade County230 kV300 MW1.0 yrs68.5
TAP169166Substation-AdjacentFLMiami-Dade County230 kV300 MW1.0 yrs68.4
FLAGAMISubstation-AdjacentFLMiami-Dade County230 kV300 MW1.0 yrs68.4
MIAMI SHORESSubstation-AdjacentFLMiami-Dade County230 kV300 MW1.0 yrs68.4
137TH AVENUESubstation-AdjacentFLMiami-Dade County230 kV300 MW1.0 yrs68.4
SWEETWATERSubstation-AdjacentFLMiami-Dade County230 kV300 MW1.0 yrs68.3

Nearby internet exchanges

See all datacenter sites in Florida →

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

Every site and score for Central District Wastewater Treat Plant, Miami, Miami Dade, Florida is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.