At a glance

BORDEN CO is a 230 kV electric substation in Texas on ONCOR ELECTRIC DELIVERY CO.'s transmission network, recorded in the HIFLD transmission dataset. 1 transmission line connect to it. 200 of Texas's 1,426 named substations operate in a higher voltage band. The highest-scoring datacenter candidate site within about 25 miles is UNKNOWN301484 in Howard County, with a DC Readiness score of 64/100.

BORDEN CO is an electric transmission substation in Texas, on ONCOR ELECTRIC DELIVERY CO.'s transmission network. It is classified as high-voltage (230 kv) and connects 1 transmission line. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Min voltage69 kV
Voltage classHigh-voltage (230 kV)
Connected lines1

Ownership

Line owner (most lines)ONCOR ELECTRIC DELIVERY CO.
StateTexas
Coordinates32.5616, -101.5968

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#309300230 kVLYNTEGAR ELECTRIC COOP, INCIN SERVICE34.1 mi
#301008138 kVONCOR ELECTRIC DELIVERY CO.IN SERVICE49.7 mi
#301316138 kVONCOR ELECTRIC DELIVERY CO.IN SERVICE16.8 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of BORDEN CO, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near BORDEN CO substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN301484Substation-AdjacentTXHoward County345 kV600 MW3.5 yrs63.6
UNKNOWN300682Substation-AdjacentTXHoward County345 kV600 MW3.5 yrs63.2
OZ HowardGreenfieldTXHoward——3.5 yrs62.1
UNKNOWN310087Substation-AdjacentTXMartin County345 kV600 MW3.5 yrs61.6
UNKNOWN303793Substation-AdjacentTXBorden County345 kV600 MW3.5 yrs60.9
UNKNOWN305803Substation-AdjacentTXBorden County345 kV600 MW3.5 yrs60.2
OZ DawsonGreenfieldTXDawson——3.5 yrs59.6
UNKNOWN303007Substation-AdjacentTXHoward County138 kV100 MW3.5 yrs57.7

How does BORDEN CO compare with other substations in Texas?

Texas has 4,939 substation records in HIFLD, of which 1,426 carry a station name; the rest are unnamed tap points, risers and line ends. 36 named substations in the state are in BORDEN CO's 230–344 kV band (3% of named stations). 200 sit in a higher band. 200 named substations in Texas operate at 345 kV or above. The highest voltage recorded in the state is 500 kV, and the state median is 138 kV.

Who owns the transmission lines at BORDEN CO?

The 3 connected lines listed above are owned by LYNTEGAR ELECTRIC COOP, INC, ONCOR ELECTRIC DELIVERY CO. Line voltages range from 138 kV to 230 kV. Their combined recorded length is about 100.6 miles.

How do candidate sites near BORDEN CO score?

The 8 highest-scoring candidate sites within about 25 miles range from 58 to 64 on the 0–100 DC Readiness scale. They fall in Howard County, Howard, Martin County, Borden County. The Texas average across 6,839 scored sites is 56.4. 3,635 of those Texas sites are classed as substation sites (candidate locations generated at an existing substation).

Frequently asked questions

What voltage is BORDEN CO substation?

BORDEN CO has a maximum voltage of 230 kV and a minimum of 69 kV. That places it in the 230–344 kV band. The median named US substation in this dataset is 115 kV, so BORDEN CO is above the national midpoint.

How many transmission lines connect to BORDEN CO substation?

1 transmission line terminate at or pass through BORDEN CO in the HIFLD line data. The connected lines listed here run at 230 kV, 138 kV. Together the listed lines cover about 100.6 miles.

Who owns BORDEN CO substation?

HIFLD does not publish substation owners directly. Most of the transmission lines that end at BORDEN CO belong to ONCOR ELECTRIC DELIVERY CO., and others to LYNTEGAR ELECTRIC COOP, INC. GridCensus derives this from the line data, so confirm ownership with the utility for anything contractual.

Where is BORDEN CO substation located?

BORDEN CO is in Texas at 32.5616, -101.5968. The datacenter candidate sites closest to it are in Howard County, Howard, Martin County.

Are there datacenter candidate sites near BORDEN CO substation?

GridCensus lists at least 8 scored candidate sites within roughly 25 miles of BORDEN CO. The highest-scoring is UNKNOWN301484 at 64/100. Across Texas, the average DC Readiness score is 56.4.

Other 230 kV substations in Texas

About this data

Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “BORDEN CO substation, Texas”, https://gridcensus.com/substations/texas/borden-co-ac1531e9 (data as of June 29, 2026).

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

Every site and score for BORDEN CO substation, Texas is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.