Skip to content
Gridcensus

NORTHEAST ANKENY

Substation

Iowa

Max voltage
161
kV

NORTHEAST ANKENY is an electric transmission substation in Iowa. It is classified as sub-transmission (138 kv) and connects 4 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage161 kV
Min voltage161 kV
Voltage classSub-transmission (138 kV)
Connected lines4

Ownership & operation

Operator not catalogued for this substation.

StateIowa
Coordinates41.7541, -93.5616

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of NORTHEAST ANKENY, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near NORTHEAST ANKENY substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
BONDURANTSubstation-AdjacentIAPolk County345 kV600 MW4.3 yrs69.3
GREATER DES MOINES ENERGY CENTERSubstation-AdjacentIAPolk County345 kV600 MW4.3 yrs69.2
SE POLKSubstation-AdjacentIAPolk County345 kV600 MW4.3 yrs69.1
GRIMESSubstation-AdjacentIADallas County345 kV600 MW4.3 yrs68.1
SYCAMORESubstation-AdjacentIAPolk County345 kV600 MW4.3 yrs68.1
NORWALKSubstation-AdjacentIAWarren County345 kV600 MW4.3 yrs67.0
BOONEVILLESubstation-AdjacentIAMadison County345 kV600 MW4.3 yrs66.6
Harriet Street Solar FieldBrownfieldIAPolk69 kV1 MW4.3 yrs65.9

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

Every site and score for NORTHEAST ANKENY substation, Iowa is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.