TAP205302 is an electric transmission substation in Idaho. It is classified as distribution (69–115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage69 kV
Min voltage69 kV
Voltage classDistribution (69–115 kV)
Connected lines3

Ownership & operation

Operator not catalogued for this substation.

StateIdaho
Coordinates44.8615, -116.1267

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP205302, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP205302 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
EC FFE Adams CountyGreenfieldIDAdams County——5.0 yrs58.2
STARKEYSubstation-AdjacentIDAdams County138 kV100 MW5.0 yrs55.8
UNKNOWN204912Substation-AdjacentIDAdams County138 kV100 MW5.0 yrs55.8
UNKNOWN204910Substation-AdjacentIDAdams County115 kV100 MW5.0 yrs55.5
OZ AdamsGreenfieldIDAdams——5.0 yrs54.2
TAP207418Substation-AdjacentIDValley County115 kV100 MW5.0 yrs54.0
UNKNOWN204913Substation-AdjacentIDAdams County69 kV50 MW5.0 yrs53.5
UNKNOWN202995Substation-AdjacentIDAdams County69 kV50 MW5.0 yrs52.8

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

Every site and score for TAP205302 substation, Idaho is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.