Datacenter 00706759844
DatacenteractiveOR
At a glance
Datacenter 00706759844 is a datacenter at OR. The facility is catalogued at about 344,665 square feet. Among the best-connected interconnection facilities in the area, the closest is US Signal OR01 - Bend, 25 miles away, with 5 connected networks.
Facility
Where is Datacenter 00706759844 located?
The facility's recorded address is OR. Oregon has 168 catalogued datacenters, the 3rd-most of any state.
How large is Datacenter 00706759844?
Datacenter 00706759844 covers about 344,665 square feet. By footprint it ranks 9th of the 105 Oregon datacenters with a recorded floor area. The median recorded footprint in Oregon is 211,904 square feet, so this facility is larger than the typical Oregon datacenter.
What network and power infrastructure is near Datacenter 00706759844?
3 PeeringDB interconnection facilities are listed in the surrounding area; of those, the closest is US Signal OR01 - Bend, about 25 miles away. The best-connected of them, Fort Rock Data Center, has 11 networks present, against a Oregon median of 3 networks per facility. 5 other datacenters are listed in the surrounding area (within about half a degree of latitude and longitude). The highest-scoring candidate site nearby is PONDEROSA in Deschutes County, with a DC Readiness score of 66.0 out of 100 and a 500 kV substation nearby.
Nearby internet exchanges
- Fort Rock Data CenterBend, OR · 11 networks
- US Signal OR01 - BendBend, OR · 5 networks
- BendTelBend, OR · 1 networks
Other datacenters nearby
- Meta Prineville DatacenterMeta · OR
- Apple Prineville DatacenterApple · Prineville, OR
- Datacenter 00772827597OR
- Datacenter 00772827601OR
- Datacenter 01152747559OR
Nearby datacenter candidate sites
Scored candidate sites near Datacenter 00706759844, ranked by DC Readiness — useful for evaluating expansion or second-site options in the same power/fiber market.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| PONDEROSA | Substation-Adjacent | OR | Deschutes County | 500 kV | 1,000 MW | 3.5 yrs | 66.0 |
| GRIZZLY | Substation-Adjacent | OR | Jefferson County | 500 kV | 1,000 MW | 3.5 yrs | 64.7 |
| ROUND BUTTE | Substation-Adjacent | OR | Jefferson County | 500 kV | 1,000 MW | 3.5 yrs | 64.3 |
| PILOT BUTTE | Substation-Adjacent | OR | Deschutes County | 230 kV | 300 MW | 3.5 yrs | 63.6 |
| REDMOND | Substation-Adjacent | OR | Deschutes County | 230 kV | 300 MW | 3.5 yrs | 62.7 |
| TAP208673 | Substation-Adjacent | OR | Deschutes County | 115 kV | 100 MW | 3.5 yrs | 60.3 |
| TAP208672 | Substation-Adjacent | OR | Deschutes County | 115 kV | 100 MW | 3.5 yrs | 60.1 |
| OZ Jefferson | Greenfield | OR | Jefferson | — | — | 3.5 yrs | 59.8 |
See something wrong or out of date?
Frequently asked questions
What is the address of Datacenter 00706759844?
Datacenter 00706759844 is located at OR. Its coordinates are 44.2873, -120.8702.
How big is Datacenter 00706759844?
Datacenter 00706759844 covers about 344,665 square feet. That is the 9th-largest of 105 Oregon datacenters with a recorded footprint.
Which internet exchanges and carrier hotels are near Datacenter 00706759844?
GridCensus lists 3 PeeringDB interconnection facilities near Datacenter 00706759844: US Signal OR01 - Bend (25 miles, 5 networks); BendTel (27 miles, 1 networks); Fort Rock Data Center (28 miles, 11 networks).
More datacenters and hubs in Oregon
About this data
Source: PNNL datacenter atlas and OpenStreetMap facility records, deduplicated by GridCensus, as published March 7, 2026. See the methodology for how records are matched, cleaned and scored.
Cite as: GridCensus, “Datacenter 00706759844, OR”, https://gridcensus.com/datacenters/datacenter-00706759844-b1ede1e3 (data as of March 7, 2026).
Dataset updated . Screening estimates derived from public data sources.
Capacity and footprint are catalogued figures from public facility records and may lag operational changes.
Go deeper than the public screen
Every site and score for Datacenter 00706759844, OR is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.