UNKNOWN129869

Substation-Adjacent

Eau Claire, Wisconsin · MISO

DC Readiness
64.0
Good / 100

UNKNOWN129869 is a substation-adjacent datacenter candidate site in Eau Claire, Wisconsin, interconnecting through MISO. It screens at 64.0/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN129869
Substation distance0.0 mi
Substation voltage345 kV
Available capacity600 MW
LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth16
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXP901 Commerce Dr
IXP distance40.7 mi
Fiber providers10
Fiber coverage53.7%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance224.8 mi

Site characteristics

Parcel ownerNORTHERN STATES POWER CO
Land owner typeprivate
Buildability15.0/100
Land cover (NLCD)Woody Wetlands

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score68/100
Construction cost index90.8 (avg 100)

Location context

Nearest datacenter901 Commerce Dr
DC distance40.7 mi
Nearest rail8.4 mi
Nearest gas pipeline3.4 mi
Nearest fiber route126.3 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.78¢/kWh
Industrial electricity8.61¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$6,093

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
87
Speed to power15%
57
Fiber connectivity12%
21
Energy cost10%
86
Water risk8%
94
Natural hazard8%
68
Buildability7%
15
Labor market4%
50
DC cluster4%
40
Land / acreage3%
45
Construction cost3%
74
Gas pipeline2%
89
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Eau Claire, ranked by DC Readiness.

Sites near UNKNOWN129869
SiteTypeVoltageCapacityQueue waitScore
SEVEN MILESubstation-Adjacent161 kV100 MW1.4 yrs71.0
UNKNOWN161952Substation-Adjacent161 kV100 MW1.4 yrs70.8
TAP163522Substation-Adjacent161 kV100 MW1.4 yrs70.2
UNKNOWN143576Substation-Adjacent161 kV100 MW1.4 yrs70.2
UNKNOWN163509Substation-Adjacent161 kV100 MW1.4 yrs69.3
UNKNOWN131390Substation-Adjacent161 kV100 MW1.4 yrs67.1
Greenfield (UNKNOWN129869 - ARPIN)Greenfield345 kV600 MW1.4 yrs65.6
Greenfield (SEVEN MILE - TREMVAL)Greenfield161 kV100 MW1.4 yrs64.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.