Skip to content
Gridcensus

Preston County, West Virginia · PJM

DC Readiness
56.3
Good / 100

TAP140075 is a substation-adjacent datacenter candidate site in Preston County, West Virginia, interconnecting through PJM. It screens at 56.3/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP140075
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW

Speed to power

ISO / RTO regionPJM
Queue depth130
Avg queue wait3.8 yrs

Connectivity

Nearest IXPCitynet Bridgeport
IXP distance27.2 mi
Fiber providers5
Fiber coverage57.6%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score78/100

Location context

Nearest datacenterCitynet Bridgeport
DC distance27.2 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveNo
Commercial electricity10.96¢/kWh
Industrial electricity7.66¢/kWh
Cooling degree days800
Heating degree days5,000
Land price / acre$3,218

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
52
Fiber connectivity12%
39
Energy cost10%
50
Water risk8%
92
Natural hazard8%
78
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
0
Climate / cooling2%
85

Nearby comparable sites

Other scored datacenter candidate sites in Preston County, ranked by DC Readiness.

Sites near TAP140075
SiteTypeVoltageCapacityQueue waitScore
EC Coal Preston CountyGreenfield3.0 yrs60.7
EC Coal Preston CountyGreenfield3.0 yrs60.4
EC Coal Preston CountyGreenfield3.0 yrs59.3
EC Coal Preston CountyGreenfield3.0 yrs59.3
EC Near FirstEnergy AlbrightGreenfield3.0 yrs58.9
EC Near FirstEnergy AlbrightGreenfield3.0 yrs58.9
EC Coal Preston CountyGreenfield3.0 yrs58.8
EC Coal Preston CountyGreenfield3.0 yrs58.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP140075, Preston County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.