Datacenter Sites in WASHINGTON, Virginia

WASHINGTON has 62 scored datacenter candidate sites averaging 51.1/100 DC Readiness, with a catalogued aggregate of 4,100 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.

62
Candidate sites
51.1/100
Avg DC Readiness
4,100 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating

Site-selection context for WASHINGTON

Yessales_tax_exemption
Datacenter tax incentive
8.10¢/kWh
Commercial electricity
5.48¢/kWh
Industrial electricity
6
Fiber providers
Low
Water stress
$5,621
Land price / acre
1,300
Cooling degree days
4,000
Heating degree days
55°F
Mean annual temp

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

By site type

Top datacenter sites in WASHINGTON

Top datacenter sites in WASHINGTON
SiteTypeVoltageCapacityQueue waitScore
Greenfield (SULLIVAN - BROADFORD (765 KV))Greenfield500 kV1,000 MW3.7 yrs73.3
Greenfield (SULLIVAN - BROADFORD (765 KV))Greenfield500 kV1,000 MW3.7 yrs72.0
UNKNOWN156532Substation-Adjacent138 kV100 MW3.7 yrs71.9
Greenfield (SULLIVAN - BROADFORD (765 KV))Greenfield500 kV1,000 MW3.7 yrs69.0
ABINGDONSubstation-Adjacent138 kV100 MW3.6 yrs68.5
UNKNOWN117054Substation-Adjacent138 kV100 MW3.6 yrs66.7
UNKNOWN113972Substation-Adjacent138 kV100 MW3.6 yrs65.4
SALTVILLESubstation-Adjacent138 kV100 MW3.6 yrs61.3
Greenfield (UNKNOWN113972 - ABINGDON)Greenfield138 kV100 MW3.6 yrs59.1
Greenfield (SALTVILLE - HANSONVILLE)Greenfield138 kV100 MW3.6 yrs58.8
Greenfield (TAP147809 - SALTVILLE)Greenfield138 kV100 MW3.6 yrs58.2
Greenfield (SALTVILLE - HANSONVILLE)Greenfield138 kV100 MW3.6 yrs56.9
Greenfield (SALTVILLE - HANSONVILLE)Greenfield138 kV100 MW3.6 yrs56.6
Greenfield (CLINCH RIVER - TAP151951)Greenfield138 kV100 MW3.6 yrs56.1
COLUMBUS MCKINNON CORP. (OVERHEAD TRAVELING CRANE, HOIST, AND MONORAIL SYSTEM MANUFACTURING)Manufacturing49.6
DOMINION TRUSS (NOT AVAILABLE)Manufacturing49.6
TRI-TUBE, INC. (IRON AND STEEL PIPE AND TUBE MANUFACTURING FROM PURCHASED STEEL)Manufacturing49.6
GENERAL ENGINEERING CO. (FLUID POWER CYLINDER AND ACTUATOR MANUFACTURING)Manufacturing49.6
GLADE STONE, INC. (CUT STONE AND STONE PRODUCT MANUFACTURING)Manufacturing49.6
SANDVIK MINING & CONSTRUCTION USA, LLC (CUTTING TOOL AND MACHINE TOOL ACCESSORY MANUFACTURING)Manufacturing49.6
AFG INDUSTRIES, INC. (GLASS PRODUCT MANUFACTURING MADE OF PURCHASED GLASS)Manufacturing49.6
PARAMONT MFG., LLC (NOT AVAILABLE)Manufacturing49.6
PROBUILT BODY & TRAILER, INC. (MOTOR VEHICLE BODY MANUFACTURING)Manufacturing49.6
ABINGDON STEEL, INC. (FABRICATED STRUCTURAL METAL MANUFACTURING)Manufacturing49.6
BRISTOL COMPRESSORS, INC. (AIR-CONDITIONING & WARM AIR HEATING EQUIPMENT & COMMERCIAL AND INDUSTRIAL REFRIGERATION EQUIPMENT MFG.)Manufacturing49.6

WASHINGTON datacenter FAQ

How many datacenter sites are in WASHINGTON?
62 scored datacenter candidate sites, averaging 51.1/100 DC Readiness.
Does WASHINGTON offer datacenter tax incentives?
Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.
What is the natural-hazard risk in WASHINGTON?
FEMA's National Risk Index rates WASHINGTON as "Relatively Moderate" (score 30).
What are industrial electricity rates in WASHINGTON?
Average industrial electricity is 5.48¢/kWh and commercial is 8.10¢/kWh in WASHINGTON.

Dataset updated . Screening estimates derived from public data sources.