Pittsylvania has 39 scored datacenter candidate sites averaging 54.4/100 DC Readiness, with a catalogued aggregate of 1,300 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.

39
Candidate sites
54.4/100
Avg DC Readiness
1,300 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in Pittsylvania

Site-selection context for Pittsylvania

Yessales_tax_exemption
Datacenter tax incentive
7.02¢/kWh
Commercial electricity
6.22¢/kWh
Industrial electricity
8
Fiber providers
Low
Water stress
$3,197
Land price / acre
1,300
Cooling degree days
4,000
Heating degree days
55°F
Mean annual temp

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

By site type

Top datacenter sites in Pittsylvania

Top datacenter sites in Pittsylvania
SiteTypeVoltageCapacityQueue waitScore
OZ PittsylvaniaGreenfield3.1 yrs59.9
OZ PittsylvaniaGreenfield3.1 yrs55.3
TAP146712Substation-Adjacent115 kV100 MW3.8 yrs52.0
BANISTERSubstation-Adjacent138 kV100 MW3.8 yrs51.6
SMITH MOUNTAINSubstation-Adjacent138 kV100 MW3.8 yrs51.6
Greenfield (SMITH MOUNTAIN - BANISTER)Greenfield138 kV100 MW1.0 yrs51.3
Greenfield (SMITH MOUNTAIN - BANISTER)Greenfield138 kV100 MW1.0 yrs51.3
CHATHAMSubstation-Adjacent115 kV100 MW3.8 yrs51.2
UNKNOWN114631Substation-Adjacent115 kV100 MW3.8 yrs51.2
UNKNOWN114491Substation-Adjacent115 kV100 MW3.8 yrs51.2
UNKNOWN114489Substation-Adjacent115 kV100 MW3.8 yrs51.2
BEARSKINSubstation-Adjacent115 kV100 MW3.8 yrs51.2
MT AIRYSubstation-Adjacent115 kV100 MW3.8 yrs51.2
Cane Creek CentreShovel-Ready3.8 yrs50.2
Southern Virginia Megasite at Berry HillShovel-Ready3.8 yrs50.2
Cherrystone Industrial ParkShovel-Ready3.8 yrs50.2
Gretna Industrial ParkShovel-Ready3.8 yrs50.2
Blairs Crossing Lot 1Shovel-Ready3.8 yrs50.2
58 East Data CampusShovel-Ready3.8 yrs50.1
Mine SiteFormer Mine3.8 yrs49.8
NAPA BuildingShovel-Ready3.8 yrs49.8
Cane Creek Centre Shell BuildingShovel-Ready3.8 yrs49.8
2000 Cane Creek PkwyShovel-Ready3.8 yrs49.7
Cane Creek Centre Advanced Manufacturing ComplexShovel-Ready3.8 yrs49.7
Cane Creek Centre, Lot 10Shovel-Ready3.8 yrs49.6

Pittsylvania datacenter FAQ

How many datacenter sites are in Pittsylvania?
39 scored datacenter candidate sites, averaging 54.4/100 DC Readiness.
Does Pittsylvania offer datacenter tax incentives?
Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.
What is the natural-hazard risk in Pittsylvania?
FEMA's National Risk Index rates Pittsylvania as "Relatively Moderate" (score 30).
What are industrial electricity rates in Pittsylvania?
Average industrial electricity is 6.22¢/kWh and commercial is 7.02¢/kWh in Pittsylvania.

Dataset updated . Screening estimates derived from public data sources.