Pickett Park

Shovel-Ready

Nottoway County, Virginia · PJM

DC Readiness
47.0
Fair / 100

Pickett Park is a shovel-ready datacenter candidate site in Nottoway County, Virginia, interconnecting through PJM. It screens at 47.0/100 DC Readiness.

Power & interconnection

Speed to power

ISO / RTO regionPJM
Queue depth864

Connectivity

Nearest IXPEdgeConneX Richmond (EDCRIC01)
IXP distance47.9 mi

Site characteristics

Site typeShovel-Ready
Acreage437 ac

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score70/100

Location context

Nearest datacenterMicrosoft Boydton Data Center
DC distance35.0 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity6.80¢/kWh
Industrial electricity5.55¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$4,440

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
38
Fiber connectivity12%
32
Energy cost10%
50
Water risk8%
88
Natural hazard8%
70
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
61
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Nottoway County, ranked by DC Readiness.

Sites near Pickett Park
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN116253Substation-Adjacent115 kV100 MW3.1 yrs65.4
TAP148046Substation-Adjacent115 kV100 MW3.0 yrs64.5
CREWESubstation-Adjacent115 kV100 MW3.1 yrs63.0
Greenfield (UNKNOWN116253 - CREWE)Greenfield115 kV100 MW3.1 yrs58.2
Greenfield (JETERSVILLE - TAP148046)Greenfield115 kV100 MW3.0 yrs55.7
Greenfield (UNKNOWN114496 - CREWE)Greenfield115 kV100 MW3.1 yrs54.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.