Former Plow & Hearth Headquarters

Shovel-Ready

Madison County, Virginia · PJM

DC Readiness
51.3
Fair / 100

Former Plow & Hearth Headquarters is a shovel-ready datacenter candidate site in Madison County, Virginia, interconnecting through PJM. It screens at 51.3/100 DC Readiness and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

UtilityRAPPAHANNOCK ELECTRIC COOPcooperativemoderate to large load · terms ≥ 25 MW

Speed to power

Interconnection outlookConstrained
≈ 3.8 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionPJM
Queue depth878
Avg queue wait3.8 yrs

Connectivity

Nearest IXPEquinix CU1/CU2/CU3/CU4 - Culpeper
IXP distance18.4 mi
Fiber providers2
Fiber coverage50.6%

Site characteristics

Site typeShovel-Ready

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score70/100

Location context

Nearest datacenterEquinix CU2
DC distance18.4 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.09¢/kWh
Industrial electricity7.53¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$6,994

Regulatory climate

Moderatestate posture · as of 2026-08

Largest US DC market; incentive preserved but a new $0.011/kWh DC electricity tax starts Jul 2026.

DC tax incentiveYes
Large-load threshold≥ 25 MW

Dominion GS-5 large-load rate (≥25 MW, ~$1.5M/MW collateral, 14-yr term) effective 2027.

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 5 nearby

Get alerts

Track Former Plow & Hearth Headquarters

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
38
Fiber connectivity12%
66
Energy cost10%
50
Water risk7%
88
Natural hazard6%
70
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
60

Nearby comparable sites

Other scored datacenter candidate sites in Madison County, ranked by DC Readiness.

Sites near Former Plow & Hearth Headquarters
SiteTypeVoltageCapacityQueue waitScore
PRATT'SSubstation-Adjacent115 kV100 MW3.8 yrs57.4
Estes PropertyShovel-Ready——3.8 yrs51.8
Springbrook FarmShovel-Ready——3.8 yrs51.7
South Park CentreShovel-Ready——3.8 yrs51.3
Criglersville School SiteIndustrial——3.8 yrs49.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Former Plow & Hearth Headquarters, Madison County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.