Skip to content
Gridcensus

Fluvanna County, Virginia · PJM

DC Readiness
62.8
Good / 100

CUNNINGHAM is a substation-adjacent datacenter candidate site in Fluvanna County, Virginia, interconnecting through PJM. It screens at 62.8/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationCUNNINGHAM
Substation distance0.0 mi
Substation voltage500 kV
Available capacity1,000 MW

Speed to power

ISO / RTO regionPJM
Queue depth878
Avg queue wait3.8 yrs

Connectivity

Nearest IXPEquinix CU1/CU2/CU3/CU4 - Culpeper
IXP distance45.9 mi
Fiber providers4
Fiber coverage91.0%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score70/100

Location context

Nearest datacenterEquinix CU2
DC distance45.9 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity7.89¢/kWh
Industrial electricity6.00¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$4,915

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
100
Speed to power15%
38
Fiber connectivity12%
45
Energy cost10%
50
Water risk8%
88
Natural hazard8%
70
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Fluvanna County, ranked by DC Readiness.

Sites near CUNNINGHAM
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN116432Substation-Adjacent230 kV300 MW3.8 yrs60.7
EC Near Bremo BluffGreenfield3.1 yrs60.7
EC Near Bremo BluffGreenfield3.1 yrs59.3
EC Near Bremo BluffGreenfield3.1 yrs58.9
EC Near Bremo BluffGreenfield3.1 yrs58.9
BEAR GARDENSubstation-Adjacent230 kV300 MW3.8 yrs58.4
UNKNOWN116461Substation-Adjacent230 kV300 MW3.8 yrs58.4
TAP146598Substation-Adjacent230 kV300 MW3.8 yrs58.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for CUNNINGHAM, Fluvanna County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.