Datacenter Sites in Campbell County, Virginia
Campbell County has 46 scored datacenter candidate sites averaging 54.9/100 DC Readiness, with a catalogued aggregate of 2,090 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
46
Candidate sites
54.9/100
Avg DC Readiness
2,090 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Campbell County
Yessales_tax_exemption
Datacenter tax incentive
7.53¢/kWh
Commercial electricity
6.12¢/kWh
Industrial electricity
7
Fiber providers
Low
Water stress
$3,656
Land price / acre
1,300
Cooling degree days
4,000
Heating degree days
55°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.
By site type
Top datacenter sites in Campbell County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| Multitrade of Pittsylvania LP | Brownfield | — | 90 MW | — | 70.8 |
| CANDLERS MOUNTAIN | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 66.5 |
| MULTITRADE OF PITTSYLVANIA LP | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 66.4 |
| OTTER RIVER | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 66.2 |
| UNKNOWN121432 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 66.2 |
| EVINGTON | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 65.9 |
| ALTAVISTA | Substation-Adjacent | 138 kV | 100 MW | 3.1 yrs | 65.8 |
| DEADEND167399 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 64.9 |
| TAP146711 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 64.3 |
| OTTER | Substation-Adjacent | 138 kV | 100 MW | 3.1 yrs | 64.0 |
| TAP146717 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 63.9 |
| UNKNOWN121377 | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 63.4 |
| TAP171701 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 62.5 |
| Greenfield (CANDLERS MOUNTAIN - SMITH MOUN) | Greenfield | 138 kV | 100 MW | 3.0 yrs | 62.2 |
| PERTH | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 60.4 |
| OZ Campbell | Greenfield | — | — | 3.1 yrs | 60.3 |
| ALTAVISTA | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 59.9 |
| Greenfield (TAP146711 - TAP171701) | Greenfield | 115 kV | 100 MW | 3.1 yrs | 59.9 |
| TAP175462 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 59.5 |
| Greenfield (CANDLERS MOUNTAIN - SMITH MOUN) | Greenfield | 138 kV | 100 MW | 3.0 yrs | 58.1 |
| Greenfield (ALTAVISTA POWER STATION - UNKN) | Greenfield | 115 kV | 100 MW | 3.1 yrs | 57.1 |
| OZ Campbell | Greenfield | — | — | 3.1 yrs | 56.7 |
| Greenfield (UNKNOWN121433 - TAP147422) | Greenfield | 115 kV | 100 MW | 3.0 yrs | 53.6 |
| Mount Athos Site | Shovel-Ready | — | — | — | 49.4 |
| Airport Commerce Park | Shovel-Ready | — | — | — | 49.3 |
Campbell County datacenter FAQ
- How many datacenter sites are in Campbell County?
- 46 scored datacenter candidate sites, averaging 54.9/100 DC Readiness.
- Does Campbell County offer datacenter tax incentives?
- Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.
- What is the natural-hazard risk in Campbell County?
- FEMA's National Risk Index rates Campbell County as "Relatively Moderate" (score 30).
- What are industrial electricity rates in Campbell County?
- Average industrial electricity is 6.12¢/kWh and commercial is 7.53¢/kWh in Campbell County.
Dataset updated . Screening estimates derived from public data sources.