FREEMAN DP
Substation-AdjacentBrunswick County, Virginia · PJM
FREEMAN DP is a substation-adjacent datacenter candidate site in Brunswick County, Virginia, interconnecting through PJM. It screens at 55.9/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.
Power & interconnection
Speed to power
Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.
Connectivity
Site characteristics
Risk & environment
Location context
Regulatory climate
Largest US DC market; incentive preserved but a new $0.011/kWh DC electricity tax starts Jul 2026.
Dominion GS-5 large-load rate (≥25 MW, ~$1.5M/MW collateral, 14-yr term) effective 2027.
Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.
Site location
Get alerts
Track FREEMAN DP
Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.
Full DC Readiness breakdown
All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.
Nearby comparable sites
Other scored datacenter candidate sites in Brunswick County, ranked by DC Readiness.
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| EC Coal Brunswick County | Greenfield | — | — | 3.1 yrs | 59.1 |
| Greenfield (UNKNOWN175463 - UNKNOWN175464) | Greenfield | 500 kV | 1,000 MW | 3.8 yrs | 58.3 |
| Greenfield (UNKNOWN175463 - UNKNOWN175464) | Greenfield | 500 kV | 1,000 MW | 3.8 yrs | 58.1 |
| TAP161135 | Substation-Adjacent | 115 kV | 100 MW | 3.8 yrs | 56.6 |
| UNKNOWN161132 | Substation-Adjacent | 115 kV | 100 MW | 3.8 yrs | 56.6 |
| LAWRENCEVILLE | Substation-Adjacent | 115 kV | 100 MW | 3.8 yrs | 56.6 |
| BRODNAX | Substation-Adjacent | 115 kV | 100 MW | 3.8 yrs | 56.5 |
| UNKNOWN161133 | Substation-Adjacent | 115 kV | 100 MW | 3.8 yrs | 56.2 |
Dataset updated . Screening estimates derived from public data sources.
Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.
Go deeper than the public screen
Every site and score for FREEMAN DP, Brunswick County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.