Skip to content
Gridcensus

Ward County, Texas · ERCOT

DC Readiness
52.9
Fair / 100

At a glance

WARD SWITCH is a substation-adjacent datacenter candidate site in Ward County, Texas, scoring 52.9/100 DC Readiness — 22nd of 32 scored sites in the county. Its nearest substation is WARD SWITCH (0 mi, 69 kV). It sits in the ERCOT grid region and the ONCOR ELECTRIC DELIVERY COMPANY LLC service territory, where interconnection has averaged 3.5 years from request to operation. GridCensus catalogs 50 MW of candidate capacity here.

Power & interconnection

Nearest substationWARD SWITCH
Nearest grid bottleneckPALOUS_WOLFCA1_1 · 36 km (ERCOT)
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityONCOR ELECTRIC DELIVERY COMPANY LLCinvestor ownedfavorable to large load · terms ≥ 75 MWERCOT connect-and-manage + SB 6 large-load provisions (≥75 MW)

Speed to power

Texas note: Since August 3, 2026, ERCOT has paused approvals to energize new datacenter and crypto-mining loads of 75 MW or more until a verification audit and a community impact review are complete; both reports are due to the Public Utility Commission of Texas by December 10, 2026. ERCOT speed-to-power scores here were set before the pause and do not reflect it. ERCOT board update.

Interconnection outlookConstrained
≈ 3.5 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionERCOT
Queue depth1,169
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Fiber providers1
Fiber coverage1.8%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score45/100

Location context

Nearest datacenterIONIC Digital Cedarvale
DC distance37.0 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Cooling degree days2,600
Heating degree days1,800
Land price / acre$1,747

Regulatory climate

Favorablestate posture · as of 2026-08

No statewide moratorium, but since Aug 3, 2026 ERCOT has paused approvals to energize new datacenter and crypto loads ≥75 MW pending an audit due Dec 10, 2026. SB 6 adds large-load obligations above 75 MW.

DC tax incentiveYes
Large-load threshold≥ 75 MW

SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track WARD SWITCH

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does WARD SWITCH compare with other sites in Ward County?

WARD SWITCH ranks 22nd of 32 scored candidate sites in Ward County. Its 52.9/100 is roughly in line with the county average of 54.4. It is roughly in line with the Texas average of 56.4 and roughly in line with the national average of 53.2.

Against the Texas average, its strongest sub-score is speed to power (78 vs 72) and its weakest is fiber connectivity (44 vs 71). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is WARD SWITCH to power, fiber and other datacenters?

The nearest mapped substation, WARD SWITCH, is about 0 miles away and operates at 69 kV. The nearest located transmission bottleneck is PALOUS_WOLFCA1_1 (ERCOT), 22 miles away. 1 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is IONIC Digital Cedarvale, 37 miles away.

What are the flood, water and hazard risks at WARD SWITCH?

At the county level, FEMA's National Risk Index rates Ward County "Very High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
78
Fiber connectivity12%
44
Energy cost10%
50
Water risk7%
44
Natural hazard6%
45
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Ward County, ranked by DC Readiness.

Sites near WARD SWITCH
SiteTypeVoltageCapacityQueue waitScore
PERMIAN BASIN 345Substation-Adjacent345 kV600 MW3.5 yrs64.6
EC Near Permian BasinGreenfield——3.5 yrs59.1
EC Near Permian BasinGreenfield——3.5 yrs58.5
UNKNOWN301432Substation-Adjacent345 kV600 MW3.5 yrs58.4
EC Near Permian BasinGreenfield——3.5 yrs58.0
EC Near Permian BasinGreenfield——3.5 yrs57.9
EC Near Permian BasinGreenfield——3.5 yrs57.9
EC Near Permian BasinGreenfield——3.5 yrs57.2

WARD SWITCH: common questions

What is the DC Readiness score of WARD SWITCH?

WARD SWITCH scores 52.9/100 on the GridCensus DC Readiness scale, rated fair. It ranks 22nd of 32 scored sites in Ward County. The Ward County average is 54.4 and the Texas average is 56.4.

What is the nearest substation to WARD SWITCH?

The nearest mapped substation is WARD SWITCH, about 0 miles away, at 69 kV. GridCensus catalogs 50 MW of candidate capacity for the site.

Which electric utility serves WARD SWITCH?

ONCOR ELECTRIC DELIVERY COMPANY LLC (investor owned) holds the retail service territory that contains the site.

What grid region is WARD SWITCH in?

WARD SWITCH is in the ERCOT region. Projects interconnecting there have averaged a 3.5-year wait from queue request to operation.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “WARD SWITCH, Ward County, TX”, https://gridcensus.com/datacenter-sites/texas/ward-county/ward-switch-4ba46502 (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for WARD SWITCH, Ward County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.