UNKNOWN302806

Substation-Adjacent

Red River, Texas · ERCOT

DC Readiness
50.6
Fair / 100

UNKNOWN302806 is a substation-adjacent datacenter candidate site in Red River, Texas, interconnecting through ERCOT. It screens at 50.6/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN302806
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityONCOR ELECTRIC DELIVERY COMPANY LLCinvestor ownedfavorable to large load · terms ≥ 75 MWERCOT connect-and-manage + SB 6 large-load provisions (≥75 MW)

Speed to power

Interconnection outlookFavorable
≈ 1.7 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionERCOT
Queue depth1,198
Avg queue wait1.7 yrs

Connectivity

Nearest IXPARE-ON Hope
IXP distance83.7 mi
Fiber providers4
Fiber coverage64.7%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score45/100

Location context

Nearest datacenterChoctaw Nation of Oklahoma Data Center
DC distance81.2 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.91¢/kWh
Industrial electricity6.84¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$3,398

Regulatory climate

Favorablestate posture · as of 2026-08

No moratorium; fastest US interconnection (ERCOT). SB 6 adds large-load obligations above 75 MW.

DC tax incentiveYes
Large-load threshold≥ 75 MW

SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN302806

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
66
Fiber connectivity12%
52
Energy cost10%
50
Water risk7%
44
Natural hazard6%
45
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Red River, ranked by DC Readiness.

Sites near UNKNOWN302806
SiteTypeVoltageCapacityQueue waitScore
EC Near River CrestGreenfield3.4 yrs60.1
EC Near River CrestGreenfield3.4 yrs59.3
EC Near River CrestGreenfield3.4 yrs57.5
EC Near River CrestGreenfield3.4 yrs57.5
EC Near River CrestGreenfield3.4 yrs56.1
EC Near River CrestGreenfield3.4 yrs55.7
EC Near River CrestGreenfield3.4 yrs55.2
EC Near River CrestGreenfield3.4 yrs55.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.