Datacenter Sites in Palo Pinto County, Texas
Palo Pinto County has 27 scored datacenter candidate sites averaging 52.7/100 DC Readiness, with a catalogued aggregate of 2,900 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
27
Candidate sites
52.7/100
Avg DC Readiness
2,900 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Palo Pinto County
Yessales_tax_exemption
Datacenter tax incentive
11.13¢/kWh
Commercial electricity
14.04¢/kWh
Industrial electricity
7
Fiber providers
Medium-High
Water stress
$2,869
Land price / acre
2,600
Cooling degree days
1,800
Heating degree days
65°F
Mean annual temp
Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
By site type
Top datacenter sites in Palo Pinto County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| TAP308178 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 63.3 |
| UNKNOWN307250 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 62.7 |
| UNKNOWN302232 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 62.4 |
| Greenfield (UNKNOWN305641 - UNKNOWN309499) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 62.2 |
| Greenfield (UNKNOWN304015 - PARKER) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 59.8 |
| Greenfield (UNKNOWN307250 - UNKNOWN302952) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 58.8 |
| UNKNOWN304174 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 58.5 |
| OZ Palo Pinto | Greenfield | — | — | 3.4 yrs | 57.8 |
| EC FFE Palo Pinto County | Greenfield | — | — | 3.4 yrs | 57.4 |
| Greenfield (TAP308178 - UNKNOWN307250) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 57.2 |
| OZ Palo Pinto | Greenfield | — | — | 3.4 yrs | 57.0 |
| Greenfield (UNKNOWN309499 - UNKNOWN303077) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 56.8 |
| Greenfield (PARKER - UNKNOWN304015) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 56.1 |
| Greenfield (UNKNOWN307250 - UNKNOWN302952) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 56.0 |
| Greenfield (UNKNOWN304174 - UNKNOWN302837) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 55.3 |
| Greenfield (UNKNOWN309499 - TAP308178) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 53.8 |
| Greenfield (TAP308178 - UNKNOWN307250) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 53.1 |
| Mine Site | Former Mine | — | — | — | 45.1 |
| Mine Site | Former Mine | — | — | — | 44.7 |
| Mine Site | Former Mine | — | — | — | 44.6 |
| Mine Site | Former Mine | — | — | — | 44.6 |
| Mine Site | Former Mine | — | — | — | 44.3 |
| Mine Site | Former Mine | — | — | — | 44.1 |
| Former U.S. Army Dempsey Heliport | Industrial | — | — | — | 43.7 |
| Mine Site | Former Mine | — | — | — | 43.6 |
Palo Pinto County datacenter FAQ
- How many datacenter sites are in Palo Pinto County?
- 27 scored datacenter candidate sites, averaging 52.7/100 DC Readiness.
- Does Palo Pinto County offer datacenter tax incentives?
- Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
- What is the natural-hazard risk in Palo Pinto County?
- FEMA's National Risk Index rates Palo Pinto County as "Very High" (score 55).
- What are industrial electricity rates in Palo Pinto County?
- Average industrial electricity is 14.04¢/kWh and commercial is 11.13¢/kWh in Palo Pinto County.