MISSOURI CITY

Substation-Adjacent

Fort Bend County, Texas · ERCOT

DC Readiness
60.2
Good / 100

MISSOURI CITY is a substation-adjacent datacenter candidate site in Fort Bend County, Texas, interconnecting through ERCOT. It screens at 60.2/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationMISSOURI CITY
Nearest grid bottleneckSTPWAP39_1 · 17 km (ERCOT)
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
UtilityCENTERPOINT ENERGYinvestor owned

Speed to power

Interconnection outlookFavorable
≈ 1.7 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionERCOT
Queue depth1,198
Avg queue wait1.7 yrs

Connectivity

Nearest IXPDatabank Houston Galleria (HOU5)
IXP distance9.5 mi
Fiber providers15
Fiber coverage90.3%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score45/100

Location context

Nearest datacenterRice Data Center
DC distance6.1 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.04¢/kWh
Industrial electricity6.44¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$4,398

Regulatory climate

Favorablestate posture · as of 2026-08

No moratorium; fastest US interconnection (ERCOT). SB 6 adds large-load obligations above 75 MW.

DC tax incentiveYes
Large-load threshold≥ 75 MW

SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track MISSOURI CITY

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power20%
66
Fiber connectivity12%
92
Energy cost10%
50
Water risk7%
44
Natural hazard6%
45
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Fort Bend County, ranked by DC Readiness.

Sites near MISSOURI CITY
SiteTypeVoltageCapacityQueue waitScore
FRANZSubstation-Adjacent345 kV600 MW1.7 yrs67.6
EC Near Imperial Power Plant LLCGreenfield——3.4 yrs66.5
SMITHERSSubstation-Adjacent345 kV600 MW1.7 yrs66.2
EC Near Jack Fusco Energy CenterGreenfield——3.4 yrs66.2
O'BRIENSubstation-Adjacent345 kV600 MW1.7 yrs65.8
EC Near Imperial Power Plant LLCGreenfield——3.4 yrs65.5
EC Near Imperial Power Plant LLCGreenfield——3.4 yrs65.5
OZ Fort BendGreenfield——3.4 yrs64.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for MISSOURI CITY, Fort Bend County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.