Mine Site

Former Mine

Denton County, Texas · ERCOT

DC Readiness
55.7
Good / 100

Mine Site is a former mine datacenter candidate site in Denton County, Texas, interconnecting through ERCOT. It screens at 55.7/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest grid bottleneck1395__A · 62 km (ERCOT)
UtilityTEXAS-NEW MEXICO POWER COinvestor ownedfavorable to large load · terms ≥ 75 MWSB 6 large-load provisions (≥75 MW)

Speed to power

Texas note: Since August 3, 2026, ERCOT has paused approvals to energize new datacenter and crypto-mining loads of 75 MW or more until a verification audit and a community impact review are complete; both reports are due to the Public Utility Commission of Texas by December 10, 2026. ERCOT speed-to-power scores here were set before the pause and do not reflect it. ERCOT board update.

Interconnection outlookConstrained
≈ 3.5 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionERCOT
Queue depth1,169
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPCyrusOne Dallas (Lewisville)
IXP distance15.1 mi
Fiber providers25
Fiber coverage88.3%

Site characteristics

Site typeFormer Mine
Former useMining: Nonmetal; Status: Abandoned
Cleanup statusAbandoned

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score45/100

Location context

Nearest datacenterCITIGROUP TECHNOLOGY INC
DC distance13.9 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.11¢/kWh
Industrial electricity11.30¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$12,287

Regulatory climate

Favorablestate posture · as of 2026-08

No statewide moratorium, but since Aug 3, 2026 ERCOT has paused approvals to energize new datacenter and crypto loads ≥75 MW pending an audit due Dec 10, 2026. SB 6 adds large-load obligations above 75 MW.

DC tax incentiveYes
Large-load threshold≥ 75 MW

SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Mine Site

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
78
Fiber connectivity12%
87
Energy cost10%
50
Water risk7%
44
Natural hazard6%
45
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Denton County, ranked by DC Readiness.

Sites near Mine Site
SiteTypeVoltageCapacityQueue waitScore
CARROLLTON FRANKFORDSubstation-Adjacent345 kV600 MW3.5 yrs69.4
LEWISVILLE SWITCHSubstation-Adjacent345 kV600 MW3.5 yrs69.0
UNKNOWN310303Substation-Adjacent345 kV600 MW3.5 yrs68.8
UNKNOWN304847Substation-Adjacent345 kV600 MW3.5 yrs68.3
DFW Gas RecoveryBrownfield14 kV12 MW3.5 yrs68.2
DENTON WEST INTERCHANGESubstation-Adjacent345 kV600 MW3.5 yrs68.0
EC Near SpencerGreenfield——3.5 yrs67.4
COOPER CREEKSubstation-Adjacent345 kV600 MW3.5 yrs67.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Mine Site, Denton County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.