Mine Site

Former Mine

Van Buren County, Tennessee · SERC

DC Readiness
54.9
Fair / 100

Mine Site is a former mine datacenter candidate site in Van Buren County, Tennessee, interconnecting through SERC. It screens at 54.9/100 DC Readiness and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

UtilitySEQUACHEE VALLEY ELECTRIC COOPcooperativefavorable to large load · state default

Speed to power

Interconnection outlookFavorable
≈ 1.0 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPPeace Communications CHA1
IXP distance44.4 mi
Fiber providers3
Fiber coverage99.3%

Site characteristics

Site typeFormer Mine
Land contactVan Buren County County Assessor
Former useMining: Stone; Status: Abandoned
Cleanup statusAbandoned

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score62/100

Location context

Nearest datacenterPeace Communications CHA1
DC distance44.4 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.69¢/kWh
Industrial electricity6.32¢/kWh
Cooling degree days1,600
Heating degree days3,600
Land price / acre$4,510

Regulatory climate

Favorablestate posture · as of 2026-08

TVA territory, DC-friendly; fast vertically-integrated interconnection.

DC tax incentiveYes
Large-load threshold≥ 50 MW

TVA infrastructure-cost provisions apply to very large loads.

Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Mine Site

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
73
Fiber connectivity12%
64
Energy cost10%
50
Water risk7%
90
Natural hazard6%
62
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
47
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
45

Nearby comparable sites

Other scored datacenter candidate sites in Van Buren County, ranked by DC Readiness.

Sites near Mine Site
SiteTypeVoltageCapacityQueue waitScore
EC Coal Van Buren CountyGreenfield——3.7 yrs59.0
OZ Van BurenGreenfield——3.7 yrs58.7
Mine SiteFormer Mine——1.0 yrs55.7
Mine SiteFormer Mine——1.0 yrs55.6
Mine SiteFormer Mine——1.0 yrs55.3
Mine SiteFormer Mine——1.0 yrs55.2
Mine SiteFormer Mine——1.0 yrs55.1
Mine SiteFormer Mine——1.0 yrs54.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Mine Site, Van Buren County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.