Former Mine

Rutherford, Tennessee · SERC

DC Readiness
55.1
Good / 100

At a glance

Former Mine site at 35.881, -86.317 is a former mine datacenter candidate site in Rutherford, Tennessee, scoring 55.1/100 DC Readiness — 39th of 40 scored sites in the county. It sits in the SERC grid region and the MIDDLE TENNESSEE E M C service territory, where interconnection has averaged 3.9 years from request to operation.

Power & interconnection

UtilityMIDDLE TENNESSEE E M Ccooperativefavorable to large load · state default

Speed to power

Interconnection outlookModerate
≈ 4.7 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSERC
Queue depth1
Avg queue wait3.9 yrs
Recent queue wait4.7 yrs
Completion rate15%
Withdrawal rate85%

Connectivity

Nearest IXPPeace Communications NSH2
IXP distance24.9 mi
Fiber providers9
Fiber coverage88.7%

Site characteristics

Site typeFormer Mine
Former useMining: Stone; Status: Abandoned
Cleanup statusAbandoned

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score62/100

Location context

Nearest datacenterTennessee South Data Center
DC distance12.7 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.81¢/kWh
Industrial electricity6.02¢/kWh
Cooling degree days1,600
Heating degree days3,600
Land price / acre$10,250

Regulatory climate

Favorablestate posture · as of 2026-08

TVA territory, DC-friendly; fast vertically-integrated interconnection.

DC tax incentiveYes
Large-load threshold≥ 50 MW

TVA infrastructure-cost provisions apply to very large loads.

Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Mine Site

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Former Mine site at 35.881, -86.317 compare with other sites in Rutherford?

Former Mine site at 35.881, -86.317 ranks 39th of 40 scored candidate sites in Rutherford. Its 55.1/100 is about 11% below the county average of 61.6. It is roughly in line with the Tennessee average of 57.0 and roughly in line with the national average of 53.2.

Against the Tennessee average, its strongest sub-score is fiber connectivity (76 vs 73) and its weakest is power availability (30 vs 42). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Former Mine site at 35.881, -86.317 to power, fiber and other datacenters?

For connectivity, the nearest internet exchange facility is Peace Communications NSH2 at 24.9 miles. 9 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Tennessee South Data Center, 12.7 miles away.

What are the flood, water and hazard risks at Former Mine site at 35.881, -86.317?

At the county level, FEMA's National Risk Index rates Rutherford "Relatively High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
59
Fiber connectivity12%
76
Energy cost10%
50
Water risk7%
90
Natural hazard6%
62
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
47
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
45

Nearby comparable sites

Other scored datacenter candidate sites in Rutherford, ranked by DC Readiness.

Sites near Former Mine site at 35.881, -86.317
SiteTypeVoltageCapacityQueue waitScore
RUTHERFORDSubstation-Adjacent500 kV1,000 MW3.9 yrs71.0
TAP155564Substation-Adjacent161 kV100 MW3.9 yrs64.4
UNKNOWN170550Substation-Adjacent161 kV100 MW3.9 yrs64.2
SMYRNASubstation-Adjacent161 kV100 MW3.9 yrs64.2
UNKNOWN170551Substation-Adjacent161 kV100 MW3.9 yrs64.1
UNKNOWN115535Substation-Adjacent161 kV100 MW3.9 yrs64.1
EC Near MTSU Power Co-Gen PlantGreenfield——3.9 yrs64.0
EC Near MTSU Power Co-Gen PlantGreenfield——3.9 yrs63.9

Former Mine site at 35.881, -86.317: common questions

What is the DC Readiness score of Former Mine site at 35.881, -86.317?

Former Mine site at 35.881, -86.317 scores 55.1/100 on the GridCensus DC Readiness scale, rated good. It ranks 39th of 40 scored sites in Rutherford. The Rutherford average is 61.6 and the Tennessee average is 57.0.

Which electric utility serves Former Mine site at 35.881, -86.317?

MIDDLE TENNESSEE E M C (cooperative) holds the retail service territory that contains the site.

What grid region is Former Mine site at 35.881, -86.317 in?

Former Mine site at 35.881, -86.317 is in the SERC region. Projects interconnecting there have averaged a 3.9-year wait from queue request to operation.

How far is Former Mine site at 35.881, -86.317 from an internet exchange?

The nearest internet exchange facility is Peace Communications NSH2, about 24.9 miles away; 9 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Former Mine site at 35.881, -86.317, Rutherford, TN”, https://gridcensus.com/datacenter-sites/tennessee/rutherford/mine-site-cc818670 (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Former Mine site at 35.881, -86.317, Rutherford is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.