WOODBURY
Substation-AdjacentCannon County, Tennessee · SERC
At a glance
WOODBURY is a substation-adjacent datacenter candidate site in Cannon County, Tennessee, scoring 59.5/100 DC Readiness — 1st of 1 scored sites in the county. Its nearest substation is WOODBURY (0 mi, 161 kV). It sits in the SERC grid region and the MIDDLE TENNESSEE E M C service territory, where interconnection has averaged 3.9 years from request to operation. GridCensus catalogs 100 MW of candidate capacity here.
Power & interconnection
Speed to power
Middle-of-the-pack interconnection conditions for this grid.
Connectivity
Site characteristics
Risk & environment
Location context
Regulatory climate
TVA territory, DC-friendly; fast vertically-integrated interconnection.
TVA infrastructure-cost provisions apply to very large loads.
Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.
Site location
Get alerts
Track WOODBURY
Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.
How does WOODBURY compare with other sites in Cannon County?
WOODBURY ranks 1st of 1 scored candidate sites in Cannon County. Its 59.5/100 is roughly in line with the county average of 59.5. It is roughly in line with the Tennessee average of 57.0 and about 12% above the national average of 53.2.
Against the Tennessee average, its strongest sub-score is power availability (60 vs 42) and its weakest is fiber connectivity (63 vs 73). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.
How close is WOODBURY to power, fiber and other datacenters?
The nearest mapped substation, WOODBURY, is about 0 miles away and operates at 161 kV. For connectivity, the nearest internet exchange facility is Peace Communications NSH2 at 37.5 miles. 4 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Tennessee South Data Center, 25.4 miles away.
What are the flood, water and hazard risks at WOODBURY?
At the county level, FEMA's National Risk Index rates Cannon County "Relatively High".
Full DC Readiness breakdown
All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.
WOODBURY: common questions
What is the DC Readiness score of WOODBURY?
WOODBURY scores 59.5/100 on the GridCensus DC Readiness scale, rated good. It ranks 1st of 1 scored sites in Cannon County. The Cannon County average is 59.5 and the Tennessee average is 57.0.
What is the nearest substation to WOODBURY?
The nearest mapped substation is WOODBURY, about 0 miles away, at 161 kV. GridCensus catalogs 100 MW of candidate capacity for the site.
Which electric utility serves WOODBURY?
MIDDLE TENNESSEE E M C (cooperative) holds the retail service territory that contains the site.
What grid region is WOODBURY in?
WOODBURY is in the SERC region. Projects interconnecting there have averaged a 3.9-year wait from queue request to operation.
How far is WOODBURY from an internet exchange?
The nearest internet exchange facility is Peace Communications NSH2, about 37.5 miles away; 4 fiber providers report service at the location.
Related pages
About this data
Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.
Cite as: GridCensus, “WOODBURY, Cannon County, TN”, https://gridcensus.com/datacenter-sites/tennessee/cannon-county/woodbury-b32ea8d1 (data as of October 10, 2026).
Dataset updated . Screening estimates derived from public data sources.
Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.
Go deeper than the public screen
Every site and score for WOODBURY, Cannon County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.