Skip to content
Gridcensus

Chesterfield County, South Carolina · SERC

DC Readiness
57.7
Good / 100

TAP150590 is a substation-adjacent datacenter candidate site in Chesterfield County, South Carolina, interconnecting through SERC. It screens at 57.7/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP150590
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPHSW-DC1RH
IXP distance41.5 mi
Fiber providers6
Fiber coverage86.2%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score60/100

Location context

Nearest datacenterDatacenter 00923167491
DC distance32.1 mi
County hazard (FEMA NRI)Relatively High (40)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.48¢/kWh
Industrial electricity7.21¢/kWh
Cooling degree days2,000
Heating degree days2,400
Land price / acre$3,318

Incentive detail: Sales tax exemption on DC equipment; fee-in-lieu of property tax for $50M+ investments.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
75
Fiber connectivity12%
44
Energy cost10%
50
Water risk8%
84
Natural hazard8%
60
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
49
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
25

Nearby comparable sites

Other scored datacenter candidate sites in Chesterfield County, ranked by DC Readiness.

Sites near TAP150590
SiteTypeVoltageCapacityQueue waitScore
EC Coal Chesterfield CountyGreenfield3.7 yrs63.7
CHERAW REID PARKSubstation-Adjacent230 kV300 MW1.0 yrs62.1
UNKNOWN121692Substation-Adjacent115 kV100 MW1.0 yrs58.5
UNKNOWN121690Substation-Adjacent115 kV100 MW1.0 yrs57.7
UNKNOWN121691Substation-Adjacent115 kV100 MW1.0 yrs57.7
Greenfield (FLAT CREEK - UNKNOWN120937)Greenfield230 kV300 MW1.0 yrs55.8
UNKNOWN121672Substation-Adjacent69 kV50 MW1.0 yrs55.7
UNKNOWN120929Substation-Adjacent69 kV50 MW1.0 yrs55.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP150590, Chesterfield County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.