UNKNOWN113144

Substation-Adjacent

Marshall County, Ohio · PJM

DC Readiness
53.7
Fair / 100

UNKNOWN113144 is a substation-adjacent datacenter candidate site in Marshall County, Ohio, interconnecting through PJM. It screens at 53.7/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN113144
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
UtilityOHIO POWER COinvestor ownedmoderate to large load · terms ≥ 25 MWData Center Tariff (≥25 MW) · 85% min take · 12 yr

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth11
Avg queue wait3.8 yrs

Connectivity

Nearest IXPDataBank Pittsburgh (PIT2)
IXP distance48.0 mi
Fiber providers2
Fiber coverage25.9%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score78/100

Location context

Nearest datacenterDataBank Pittsburgh PIT2
DC distance48.0 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveNo
Commercial electricity12.10¢/kWh
Industrial electricity7.26¢/kWh
Cooling degree days800
Heating degree days5,000
Land price / acre$3,668

Regulatory climate

Moderatestate posture · as of 2026-08

DC tax incentives paused for 2026; AEP Ohio large-load tariff in force.

DC tax incentiveNo / suspended
Large-load threshold≥ 25 MW

AEP Ohio tariff: ≥25 MW, 85% take-or-pay, on-site-gen curtailment sync.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN113144

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power20%
37
Fiber connectivity12%
56
Energy cost10%
50
Water risk7%
92
Natural hazard6%
78
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
85

Nearby comparable sites

Other scored datacenter candidate sites in Marshall County, ranked by DC Readiness.

Sites near UNKNOWN113144
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN140084Substation-Adjacent765 kV1,000 MW3.8 yrs64.9
KAMMER (765KV)Substation-Adjacent765 kV1,000 MW3.8 yrs64.8
EC Near Axiall Natrium PlantGreenfield——3.0 yrs58.6
Greenfield (KAMMER (765KV) - BELMONT)Greenfield765 kV1,000 MW3.8 yrs58.4
OZ MarshallGreenfield——3.0 yrs58.3
EC Near Axiall Natrium PlantGreenfield——3.0 yrs57.1
EC Near Axiall Natrium PlantGreenfield——3.0 yrs56.8
EC FFE Marshall CountyGreenfield——3.0 yrs56.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN113144, Marshall County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.