Huron County, Ohio · PJM

DC Readiness
56.3
Good / 100

TAP137863 is a substation-adjacent datacenter candidate site in Huron County, Ohio, interconnecting through PJM. It screens at 56.3/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP137863
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
UtilityOHIO EDISON COinvestor ownedmoderate to large load · terms ≥ 25 MW

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth11
Avg queue wait3.8 yrs

Connectivity

Nearest IXPLightSpeed Hosting - Medina
IXP distance29.8 mi
Fiber providers6
Fiber coverage64.3%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score70/100

Location context

Nearest datacenterLightSpeed Hosting - Medina
DC distance29.8 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.87¢/kWh
Industrial electricity8.05¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$7,432

Regulatory climate

Moderatestate posture · as of 2026-08

DC tax incentives paused for 2026; AEP Ohio large-load tariff in force.

DC tax incentiveNo / suspended
Large-load threshold≥ 25 MW

AEP Ohio tariff: ≥25 MW, 85% take-or-pay, on-site-gen curtailment sync.

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track TAP137863

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power20%
38
Fiber connectivity12%
69
Energy cost10%
50
Water risk7%
90
Natural hazard6%
70
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
42
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
80

Nearby comparable sites

Other scored datacenter candidate sites in Huron County, ranked by DC Readiness.

Sites near TAP137863
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN155618Substation-Adjacent138 kV100 MW3.8 yrs56.3
EC FFE Huron CountyGreenfield——3.2 yrs56.3
UNKNOWN114067Substation-Adjacent138 kV100 MW3.8 yrs55.9
UNKNOWN115208Substation-Adjacent69 kV50 MW3.8 yrs53.5
Norwalk Bargain CenterIndustrial——3.8 yrs50.7
287 West Main StreetIndustrial——3.8 yrs50.7
Bellevue Library ParcelsIndustrial——3.8 yrs50.7
Price Family PropertyIndustrial——3.8 yrs50.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.