EAST LIMA SUBSTATION

Substation-Adjacent

Allen County, Ohio · PJM

DC Readiness
63.1
Good / 100

EAST LIMA SUBSTATION is a substation-adjacent datacenter candidate site in Allen County, Ohio, interconnecting through PJM. It screens at 63.1/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationEAST LIMA SUBSTATION
Substation distance0.0 mi
Substation voltage345 kV
Available capacity600 MW

Speed to power

ISO / RTO regionPJM
Queue depth11
Avg queue wait3.8 yrs

Connectivity

Nearest IXPMicrotronix Datacenter Ottoville
IXP distance18.6 mi
Fiber providers10
Fiber coverage43.9%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score70/100

Location context

Nearest datacenterMicrotronix Datacenter Ottoville
DC distance18.6 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.97¢/kWh
Industrial electricity9.03¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$8,341

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
87
Speed to power15%
45
Fiber connectivity12%
49
Energy cost10%
50
Water risk8%
90
Natural hazard8%
70
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
42
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Allen County, ranked by DC Readiness.

Sites near EAST LIMA SUBSTATION
SiteTypeVoltageCapacityQueue waitScore
OZ AllenGreenfield3.2 yrs64.3
EC FFE Allen CountyGreenfield3.2 yrs63.7
SOUTHWEST LIMASubstation-Adjacent345 kV600 MW3.8 yrs62.9
NORTHWEST LIMASubstation-Adjacent138 kV100 MW3.8 yrs58.8
EASTOWN ROADSubstation-Adjacent138 kV100 MW3.8 yrs57.8
FORD LIMASubstation-Adjacent138 kV100 MW3.8 yrs57.6
ROCKPORTSubstation-Adjacent138 kV100 MW3.8 yrs57.4
UNKNOWN113684Substation-Adjacent138 kV100 MW3.8 yrs57.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.