Datacenter Sites in Adams County, North Dakota

Adams County has 14 scored datacenter candidate sites averaging 63.7/100 DC Readiness, with a catalogued aggregate of 2,900 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.

14
Candidate sites
63.7/100
Avg DC Readiness
2,900 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 6 in Adams County

Site-selection context for Adams County

Yesproperty_tax_exemption
Datacenter tax incentive
10.07¢/kWh
Commercial electricity
7.57¢/kWh
Industrial electricity
3
Fiber providers
Low-Medium
Water stress
$1,552
Land price / acre
500
Cooling degree days
8,600
Heating degree days
40°F
Mean annual temp

Incentive detail: Property tax exemption for new DC construction for up to 5 years.

By site type

Top datacenter sites in Adams County

Top datacenter sites in Adams County
SiteTypeVoltageCapacityQueue waitScore
HETTINGERSubstation-Adjacent230 kV300 MW3.3 yrs62.5
UNKNOWN135231Substation-Adjacent115 kV100 MW3.3 yrs58.1
UNKNOWN201993Substation-Adjacent115 kV100 MW3.3 yrs58.1
TAP160706Substation-Adjacent69 kV50 MW3.3 yrs56.1
UNKNOWN157617Substation-Adjacent69 kV50 MW3.3 yrs56.1
Mine SiteFormer Mine3.3 yrs55.7

Adams County datacenter FAQ

How many datacenter sites are in Adams County?
14 scored datacenter candidate sites, averaging 63.7/100 DC Readiness.
Does Adams County offer datacenter tax incentives?
Property tax exemption for new DC construction for up to 5 years.
What is the natural-hazard risk in Adams County?
FEMA's National Risk Index rates Adams County as "Relatively Low" (score 20).
What are industrial electricity rates in Adams County?
Average industrial electricity is 7.57¢/kWh and commercial is 10.07¢/kWh in Adams County.

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen