DC Readiness
51.8
Fair / 100

Grover Industries is an industrial datacenter candidate site in Polk County, North Carolina, interconnecting through PJM. It screens at 51.8/100 DC Readiness and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

UtilityDUKE ENERGY CAROLINAS, LLCinvestor ownedmoderate to large load · terms ≥ 100 MWLarge Load Customer terms (≥100 MW): minimum bills, contract demand · 10 yr

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth177
Avg queue wait3.8 yrs

Connectivity

Nearest IXPCloudOgre
IXP distance7.6 mi
Fiber providers5
Fiber coverage59.0%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score58/100

Location context

Nearest datacenterCloudOgre
DC distance7.6 mi
County hazard (FEMA NRI)Relatively High (42)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.65¢/kWh
Industrial electricity7.88¢/kWh
Cooling degree days1,600
Heating degree days3,300
Land price / acre$7,577

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 6 nearby

Get alerts

Track Grover Industries

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
40
Fiber connectivity12%
85
Energy cost10%
50
Water risk7%
84
Natural hazard6%
58
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
45

Nearby comparable sites

Other scored datacenter candidate sites in Polk County, ranked by DC Readiness.

Sites near Grover Industries
SiteTypeVoltageCapacityQueue waitScore
CAMPOBELLOSubstation-Adjacent115 kV100 MW1.0 yrs63.9
UNKNOWN110347Substation-Adjacent100 kV50 MW3.8 yrs55.9
TAP145945Substation-Adjacent100 kV50 MW3.8 yrs55.9
Mill Spring SchoolIndustrial——3.8 yrs52.7
Mine SiteFormer Mine——3.8 yrs52.5
Swannanoa Palmisano PropertyIndustrial——3.8 yrs51.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.