DC Readiness
52.1
Fair / 100

Heart of Fletcher is an industrial datacenter candidate site in Henderson County, North Carolina, interconnecting through PJM. It screens at 52.1/100 DC Readiness and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

UtilityDUKE ENERGY CAROLINAS, LLCinvestor ownedmoderate to large load · terms ≥ 100 MWLarge Load Customer terms (≥100 MW): minimum bills, contract demand · 10 yr

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth177
Avg queue wait3.8 yrs

Connectivity

Nearest IXPNetriplex
IXP distance5.1 mi
Fiber providers11
Fiber coverage37.9%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score58/100

Location context

Nearest datacenterNetriplex
DC distance5.1 mi
County hazard (FEMA NRI)Relatively High (42)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.80¢/kWh
Industrial electricity8.63¢/kWh
Cooling degree days1,600
Heating degree days3,300
Land price / acre$11,065

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Heart of Fletcher

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
36
Fiber connectivity12%
81
Energy cost10%
50
Water risk7%
84
Natural hazard6%
58
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
45

Nearby comparable sites

Other scored datacenter candidate sites in Henderson County, ranked by DC Readiness.

Sites near Heart of Fletcher
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN110541Substation-Adjacent115 kV100 MW3.8 yrs59.2
TAP169552Substation-Adjacent115 kV100 MW3.8 yrs58.2
UNKNOWN110545Substation-Adjacent115 kV100 MW3.8 yrs58.0
HENDERSONSubstation-Adjacent115 kV100 MW3.8 yrs57.5
HORSEHOESubstation-Adjacent115 kV100 MW3.8 yrs57.5
EC Coal Henderson CountyGreenfield——4.3 yrs57.4
UNKNOWN110592Substation-Adjacent115 kV100 MW3.8 yrs57.3
TAP145614Substation-Adjacent115 kV100 MW3.8 yrs57.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Heart of Fletcher, Henderson County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.