Skip to content
Gridcensus

UNKNOWN111797

Substation-Adjacent

Bertie County, North Carolina · PJM

DC Readiness
57.6
Good / 100

UNKNOWN111797 is a substation-adjacent datacenter candidate site in Bertie County, North Carolina, interconnecting through PJM. It screens at 57.6/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN111797
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
UtilityROANOKE ELECTRIC MEMBER CORPcooperativemoderate to large load · state default

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth177
Avg queue wait3.8 yrs

Connectivity

Nearest IXPEdgeConneX Norfolk (EDCNOR01)
IXP distance70.7 mi
Fiber providers5
Fiber coverage67.1%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score58/100

Location context

Nearest datacenterEdgeConneX Norfolk (EDCNOR01)
DC distance70.7 mi
County hazard (FEMA NRI)Relatively High (42)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.89¢/kWh
Industrial electricity9.11¢/kWh
Cooling degree days1,600
Heating degree days3,300
Land price / acre$4,072

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 7 nearby

Get alerts

Track UNKNOWN111797

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power20%
36
Fiber connectivity12%
61
Energy cost10%
50
Water risk7%
84
Natural hazard6%
58
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
45

Nearby comparable sites

Other scored datacenter candidate sites in Bertie County, ranked by DC Readiness.

Sites near UNKNOWN111797
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN169539Substation-Adjacent230 kV300 MW3.8 yrs57.6
TAP169540Substation-Adjacent230 kV300 MW3.8 yrs57.6
TAP161598Substation-Adjacent230 kV300 MW3.8 yrs57.5
OZ BertieGreenfield——4.3 yrs52.2
Greenfield (EARLEYS - EVERETTS)Greenfield230 kV300 MW3.8 yrs51.5
Mine SiteFormer Mine——3.8 yrs47.9
Mine SiteFormer Mine——3.8 yrs45.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for UNKNOWN111797, Bertie County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.