Skip to content
Gridcensus

Middlesex County, New Jersey · PJM

DC Readiness
66.1
Good / 100

LAKE NELSON is a substation-adjacent datacenter candidate site in Middlesex County, New Jersey, interconnecting through PJM. It screens at 66.1/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationLAKE NELSON
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW

Speed to power

ISO / RTO regionPJM
Queue depth222
Avg queue wait3.8 yrs

Connectivity

Nearest IXPDigital Realty EWR (3 Corporate Pl)
IXP distance0.3 mi
Fiber providers10
Fiber coverage97.3%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score72/100

Location context

Nearest datacenterDatacenter 00345650474
DC distance0.2 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.80¢/kWh
Industrial electricity7.11¢/kWh
Cooling degree days1,000
Heating degree days4,900
Land price / acre$26,828

Incentive detail: UEZ sales tax exemption (reduced rate); BEIP/Grow NJ incentives for job creation.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
32
Fiber connectivity12%
100
Energy cost10%
50
Water risk8%
84
Natural hazard8%
72
Buildability7%
60
Labor market4%
50
DC cluster4%
100
Land / acreage3%
30
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Middlesex County, ranked by DC Readiness.

Sites near LAKE NELSON
SiteTypeVoltageCapacityQueue waitScore
SAYREVILLESubstation-Adjacent500 kV1,000 MW3.8 yrs71.6
DEANSSubstation-Adjacent500 kV1,000 MW3.8 yrs67.8
South Brunswick Landfill SolarBrownfield13 MW3.8 yrs67.0
UNKNOWN132955Substation-Adjacent230 kV300 MW3.8 yrs66.4
Highland Park SolarBrownfield1 MW3.8 yrs66.2
AC Redshaw Elementary School SolarBrownfield0 MW3.8 yrs66.2
METUCHENSubstation-Adjacent230 kV300 MW3.8 yrs66.0
EC Near PSEG Sewaren Generating StationGreenfield2.6 yrs65.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for LAKE NELSON, Middlesex County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.